Westerveld pumping station ready for the future
Text Roel van GilsImage Drone flight-Twente

Waterschap Drents Overijsselse Delta (WDODelta) has more than 600 automated pumping stations and weirs in its management area. To keep them in good condition, a unique renovation programme has been set up, drawing on expertise from the market through a multi-year framework agreement with three market parties: Van Heteren, Dubbink and Pannekoek. Van Heteren is currently replacing the old Westerveld pumping station, built in 1965, near Langenholterdijk 3 in Zwolle.

Pumping stations and weirs in WDODelta’s management area are renovated or replaced on average once every 25 years. “That means a large number of pumping stations and weirs need to be renovated or replaced each year. We rely heavily on the market to deliver this,” says Erik Wiggers, project manager at WDODelta. “That is why we set up the renovation programme five years ago, to commission this work over multiple years through framework agreements with various construction teams.” Van Heteren is now in its second contract period. “Together with the two other contractors, we ensure a balanced allocation. So, under the framework agreement, we do not hold mini-competitions, but decide together who is best placed to take on each asset.”

The same team
The existing Westerveld pumping station, dating from the 1960s, had reached the end of its technical service life and no longer met today’s requirements. Its capacity was also no longer sufficient. The decision was made to build a replacement on virtually the same site, with greater capacity. “In 2021, we built a similar pumping station (Cellemuiden, ed.) under the framework agreement,” says Ewout Aman, project leader at Van Heteren. “So we took on Westerveld with the same team. Partly to maintain momentum, but also to avoid reinventing the wheel. Improvements identified at Cellemuiden were incorporated straight into the design for Westerveld.” Erik adds: “That is the great thing about the renovation programme. We learn an enormous amount from each other. Thanks to the construction team approach, with experienced people on board, the lead time is extremely short, enabling us to build pumping stations like these very quickly. In the past, that would have been unthinkable under a traditional tendering process. Risks are also identified at an early stage. The water authority ultimately delivers more for less, with better quality and greater job satisfaction.”

Flood protection
For practical reasons, the new Westerveld pumping station was built next to the old one. “There was room to move it slightly, allowing the existing pumping station to remain operational during construction,” explains Ewout. “The pumping station is located in a primary flood defence. That is why we brought Witteveen+Bos into the design process, given its specialist design expertise in primary flood defences. In particular, this covered developing the double barrier system, both for the steel pressure pipes and for the fish pass, which was also newly built.” Van Heteren then began work on site in early May 2023, constructing a cofferdam on either side of the dike. “The work was carried out almost in parallel, which meant that we had finished the earthworks just before the summer construction holiday. We then completed the pipework through the dike in just three weeks. The superstructure was built next, and by mid-November the two pumps were running.” The new pumping station has two concrete volute pumps by Bosman Watermanagement, each with a capacity of 53 m3 per minute.

Westerveld pumping station is located on the route of the Stadsdijken Zwolle dike reinforcement project. “We brought the new construction forward in the schedule so that the pumping station would be ready when the dike reinforcement work began,” says Erik. “And we succeeded, as the pumps are already running. This is down to Van Heteren’s expertise. They have the knowledge, skills and resources to carry the project smoothly and effectively from design through to completion.” And the work continues: Van Heteren is already preparing the next four projects under Waterschap Drents Overijsselse Delta’s weir and pumping station renovation programme.
Question about this story? Ask your question
Who worked on it
Gemaal Westerveld in Zwolle
- construction teamVan Heteren
- Design expertiseWitteveen+Bos
- concrete volute pumpsBosman Watermanagement
Keep following this
Get an email when a new story is published. No account needed.
- ProjectGemaal Westerveld
- ThemeFlood protection and climate-resilient water management
- SubjectWater infrastructure
- CompanyVan Heteren
- CompanyWitteveen+Bos
- CompanyBosman Watermanagement
















