Westerkogge combination culvert: ‘one of a kind’

The construction of new banks and strengthening of the dike between Hoorn and Schardam is changing the water system in the polder behind Westerkogge pumping station in Scharwoude. The existing inlet could no longer be used. Vopo Pompen- en Machinefabriek BV was brought in by the Alliantie Markermeerdijken to design and build a new combination culvert. It is truly one of a kind, the result of the many requirements set by Hoogheemraadschap Hollands Noorderkwartier.

Vopo Pompen (established in 1904) has traditionally focused on manufacturing pumps for draining surface water. Over the years, the company has grown into a leading player in the professional water sector, serving public authorities, regional water authorities, water boards, provinces, municipalities and engineering consultancies throughout the Netherlands. “We offer clients a single point of contact for surface water technologies, such as (fish-friendly) pumps and pumping stations, inlets, screen cleaners, fish passes, weirs, electrical installations and pipework,” says Hans de Wit of Vopo Pompen.

Strict requirements
Although Vopo still has the character of a traditional family business and continues to build mainly high-capacity, low-head pumps, the times have moved on. Its state-of-the-art factory, which has its own pump test facility, produces some of the most sophisticated pumps. “Pump installations are often delivered on a turnkey basis, complete with automation and automatic screen cleaners,” says De Wit. “In many cases, we handle the design, manufacture, assembly, installation and aftercare, as we did here on the Markermeerdijken. Since the existing inlet at the former Westerkogge steam pumping station could no longer be used, a combination culvert was devised as an alternative. In addition to all the service-life and structural requirements, the future operator, Hoogheemraadschap Hollands Noorderkwartier, set three key requirements. The combination culvert had to provide an inlet capacity of at least 70 m3/min, allow fish migration to and from the Markermeer, and include a connection for emergency pumping at 100 m3/min.”

Pumping station control system
“These requirements make the new combination culvert a unique structure,” says De Wit. “Design work began in 2018. The biggest challenge and effort at this stage was coordinating all the disciplines precisely: civil engineering, mechanical engineering and electrical engineering. This included all the calculations and producing detailed drawings, to ensure the construction phase went smoothly. The Ø 1,000 mm pipe is fitted with two Ø 1,000 mm automatic butterfly valves, an attraction-flow pump, a Ø 800 mm connection for emergency pumping, various level measurements, an automatic screen cleaner and a complete control system, including a pumping station control system, to manage all functions. Following the design process, construction began in early 2020. The challenge then was to schedule all the work as effectively as possible within a short timeframe and with limited space in the construction pit. But we managed that too. We successfully delivered the Westerkogge combination culvert in the summer of 2020.”
Een zakelijke vraag aan Vopo pompen- en Machinefabriek B.V.? Get in touch
Who worked on it
Combiduiker Westerkogge in Koggenland
- clientAlliantie Markermeerdijken
Keep following this
Get an email when a new story is published. No account needed.
- ProjectCombiduiker Westerkogge
- ThemeFlood protection and climate-resilient water management
- SubjectWater infrastructure
- CompanyAlliantie Markermeerdijken
- CompanyVopo pompen- en Machinefabriek B.V.