Underground utilities must make way for higher Waal dike

The Waal dike contains an extensive network of utility cables and pipes serving the surrounding buildings. The dike’s core zone is being relocated as it is reinforced and raised. To prevent the cables and pipes from ending up beneath a greater depth of cover and under the new roads, Van den Heuvel is relocating them in advance of the dike works, cluster by cluster. For the family business, which has more than 65 years’ experience in underground infrastructure, the project is an unusual undertaking given the many stakeholders and the surroundings.

“We were approached by the De Betuwse Waard consortium during the tender stage to help devise the most efficient schedule possible and assess its practical feasibility,” says Ivo van Dieten of Van den Heuvel. “In effect, we are working ahead of the main team, and our work must not get in the way of its operations. We also know the Wolferen and Sprok area very well, and are, among other things, a local contractor for network operator Liander (gas and electricity) and water company Vitens. Initially, we submitted a proposal to relocate the gas pipelines and electricity cables, which were included in the tender. After the contract was awarded, all the other parties also came forward, including KPN, Ziggo, Vitens, the municipality of Overbetuwe (pressure sewer and data cable) and even Rijkswaterstaat, to relocate a number of signal cables.”

Hour-by-hour planning
Raising the Waal dike means its core zone is being relocated. “Utility companies do not want their underground infrastructure to become inaccessible later on,” says Robert van Welie, project manager at Van den Heuvel. “The only way to prevent that is to relocate the existing cables and pipes by around 20 metres. Naturally, the work is phased to minimise disruption to local residents. We start work just before the consortium does. With so many stakeholders, that is quite a challenge. As much of the work is on privately owned land, it takes close coordination and a schedule planned almost down to the hour. Clear agreements are made with residents in advance, but we also keep in touch during the work and after handover to make sure everything is properly completed. We began work in July 2021, and the phased programme will continue until 2024.”
Turnkey
Van den Heuvel handles the cable and pipe relocations on a fully turnkey basis. “As a contract contractor for Liander and Vitens, we know the area well, as well as their processes and the applicable laws and regulations,” says Van Dieten. “That makes the work much easier, and is also why the De Betuwse Waard consortium brought us on board.” He is aware that the family business will have plenty of work ahead in the coming years, particularly in view of the energy transition. “We are hard at work on underground infrastructure, ensuring all stakeholders have the right cables and pipes. And that is before we even consider what is yet to come with hydrogen and other new technologies. We are keeping a close eye on developments so we can respond in good time.”
Have a business enquiry for Van den Heuvel? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeUnderground construction
- SubjectWater infrastructure
- CompanyVan den Heuvel
- CompanyCombinatie De Betuwse Waard