No flood defence reinforcement without setting-out
Text Roel van Gils Beeld Schmitz Civieltechnische Werken

A flood defence reinforcement project calls for an integrated approach, with earthworks forming one part of the picture. From the initial design through to final handover, every layer of clay and sand must be placed exactly where it belongs. That is a job for the experts at Schmitz Civieltechnische Werken. The setting-out team has been involved in the project since late 2024, and is expected to remain involved until at least 2030.
The collaboration came about through Ploegam, part of Dijkalliantie Neder-Betuwe, with whom we have already completed several projects successfully, explains Dave Schmitz, who runs the surveying business with his brother Mike. However, a flood defence reinforcement project had not previously featured on their joint CV. “For this project, Dijkalliantie Neder-Betuwe was looking for a lead surveyor, and that is the role we fulfil, supported by specialists, hired staff and alliance employees, because it is, of course, a team effort.”
Always working from the latest version
The work began long before the first shovel went into the ground. “During the design phase, we help prepare and check the machine control models. These digital models form the basis for the GPS-guided machines working on site. The team ensures that the right data is loaded into the machines, checks versions and makes sure they are always working from the latest models. At peak times, around twenty-five to thirty machines use this digital information.”

Quality assurance
As lead surveyor, the Schmitz team acts as the link between design and construction. Quality assurance is also an important part of the work. “The embankment is made up of several layers of clay and sand, each of which must meet specific requirements,” Dave explains. “After every construction stage, checks are carried out using GPS equipment. We record the results digitally, and they later form an important part of the handover dossier.”
675 monitoring points
Monitoring settlement also plays a major role. “Hundreds of settlement plates are installed on the embankment to track ground movement,” says Mike. “At the peak of the project, we monitor around 430 settlement plates.” What is the biggest challenge for Schmitz Civieltechnische Werken on this project? “Making sure we do not overlook a single detail,” they say. Ultimately, the team will hand the client a complete digital map of the completed works, enabling the alliance to deliver a demonstrably safe, future-proof flood defence to its client, Waterschap Rivierenland.
Alongside its work on the flood defence, Schmitz works daily for a range of clients, setting out detailed measurements for concrete structures, control lines for asphalt surfacing and road markings on provincial and national roads, and even at airports. “We now do this using several robotic plotters and another GPS-guided machine.” This expertise builds on the experience of Jan Schmitz (father), who has spent more than fifteen years with the company setting out control lines digitally, using both GPS and total station systems.
Een zakelijke vraag aan Schmitz Civieltechnische Werken B.V.? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeFlood protection and climate-resilient water management
- SubjectWater infrastructure
- CompanySchmitz Civieltechnische Werken B.V.