New pumping station at an ‘inaccessible’ site

Text Roel van GilsImage Schouls

Schouls heeft de afgelopen jaren al heel wat gemalen aangepakt voor diverse waterschappen.
Schouls heeft de afgelopen jaren al heel wat gemalen aangepakt voor diverse waterschappen.

Aannemingsbedrijf Schouls BV of Koudekerk aan den Rijn has started work on pumping station Nova Zembla in Ilpendam, commissioned by Hoogheemraadschap Hollands Noorderkwartier. For this seasoned specialist in pumping station construction, the project is not so much a technical challenge, were it not for the site’s inaccessibility to large equipment. The work is therefore being carried out entirely from the water. And that brings its fair share of challenges.

These steel sheet piles will remain in place, as they will also form the walls of the inlet and outlet structures.

Pumping station Nova Zembla will replace the old Vurige Staart pumping station, further along in the polder. “This station has reached the end of its technical service life,” says Leen van Belen of Schouls. Nova Zembla will have a greater capacity than the old station and will pump water directly from the polder into the regional water system. VOPO oppervlaktewaterbeheer, the pump supplier and mechanical engineering contractor, put Schouls forward to the water board for the project. “Hoogheemraadschap Hollands Noorderkwartier had tasked them with finding a contractor for the civil engineering works through a tender. So we are both now working for the water board, with Schouls acting as main contractor and taking care of overall coordination.”

All equipment and materials are transported to and from the site by pontoon, which makes the project quite unusual and labour-intensive.

Using pontoons

The site for the new pumping station was carefully selected. “The biggest challenge at this site is access,” says Leen. “There is a cycle path along the embankment, but it is not suitable for heavy equipment. The initial idea was to access the site from the polder side, but the poor ground conditions made that impossible.” The work must be carried out to a strict schedule, from October 2023 to March 2024 inclusive, because of the local flora and fauna. “That left us with just one option: access by water. But that has quite a few implications. It is a 500-metre journey by boat to the worksite. We are used to working where land and water meet, but usually equipment and materials can still be transported overland. That is not possible here. Everything is handled from pontoons, which makes the project quite unusual and labour-intensive. The logistics have to be perfectly organised. If something is missing, it means another trip back and forth, which is best avoided.”

Impression of pumping station Nova Zembla.

Cofferdam walls 

Pumping station Nova Zembla has a single pump and an automatic screen cleaner supplied by VOPO. “We started by building the cofferdam using steel sheet piles. These will remain in place, as they will also form the walls of the inlet and outlet structures. We then installed foundation piles and poured the underwater concrete floor. This allows us to build the pumping station in stages, starting on the regional water system side and moving towards the polder side, which is 2 metres lower, before working our way back. The polder side will then be fully completed, including the pump and pipework supplied by VOPO, before we start fitting out the regional water system side. Otherwise, we would no longer be able to access it.” Leen says Schouls’ work is still right on schedule. “Let’s hope we don’t lose too many days to bad weather. We are not working in the most favourable season, after all. But as things stand, we expect to be finished in March.”

The work must be carried out to a strict schedule, from October 2023 to March 2024 inclusive, because of the local flora and fauna.

Over the past few years, Schouls has worked on many pumping stations for various water boards. “We have framework contracts with three water boards for the construction, maintenance and renovation of polder pumping stations, and are currently building new pumping stations in Aalsmeer and Den Hoorn as well.” After 70 years in Leiden, Schouls recently moved from Leiden to a new, energy-neutral office in Koudekerk aan de Rijn. “That puts us in a strong position for the future.”   

Een zakelijke vraag aan Vopo pompen- en Machinefabriek B.V.? Get in touch

Who worked on it

Nova Zembla in Waterland

  1. pump supplierVOPO
  2. main contractorAannemingsbedrijf Schouls BV

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectNova Zembla
  • ThemeFlood protection and climate-resilient water management
  • SubjectWater infrastructure
  • CompanyVopo pompen- en Machinefabriek B.V.
  • CompanyAannemingsbedrijf Schouls BV
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.