Keeping a constant check on dike safety

Voordeel van GIS is dat iedereen altijd over de laatste versie beschikt van een document of tekening.
Voordeel van GIS is dat iedereen altijd over de laatste versie beschikt van een document of tekening.

One of the key objectives of the dike reinforcement project is to ensure a safe dike for the next 50 years, by the end of 2025 at the latest. “We need to keep a constant check on dike safety,” says technical manager Gerjan Westerhof. To achieve this, the Graaf Reinaldalliantie is investing heavily in digitising and automating all processes, including design, calculations and drawings.

“Digitalisation helps us build safely and efficiently,” explains Gerjan Westerhof. “We are digitising everything, including calculations, working drawings, designs and monitoring instruments. Ensuring a safe dike requires a lot of data and calculations: what is the composition of the subsoil, how strong are the soil layers, what is the pore water pressure at high and low water levels, what are the effects of piping measures, and so on. By digitising all this data, calculations and designs, we can manage everything from a single source, namely GIS. This is where the design comes together. Everyone involved in the project, including land acquisition specialists, stakeholder managers and project managers, works with GIS. No paper is involved. A major advantage is that everyone always has the latest version of a document or drawing. We have better control, save time, work more efficiently, gain a clear view of interfaces, save costs and improve safety.”

“We are digitising everything, including calculations, working drawings, designs and monitoring instruments.”

Insight into current dike stability

To illustrate the importance of digitalisation, design lead Daan Jumelet gives the example of Wilma, the dike design tool. “Reinforcing a dike is no easy task. It involves a long stretch, with the dike’s geometry varying considerably, and the dike is built on heterogeneous subsoil, with varying layers of sand, peat and clay. This requires a lot of calculations. Around 80 per cent of the geotechnical design process has therefore been automated. We use Wilma, a digital design and calculation tool, for this. During the design phase, we carried out all kinds of calculations. When work actually begins, Wilma lets us rerun calculations at the touch of a button, using monitoring data, to gain insight into the dike’s current stability. This gives us a constant overview of dike safety.”

Thanks to monitoring, including real-time settlement marker measurements and pore water pressure measurements, work on the dike can continue during the high-water season.

Continuing work during the high-water season

Monitoring instruments are another form of digitalisation. Thanks to monitoring, including real-time settlement marker measurements and pore water pressure measurements, work on the dike can continue during the high-water season. The risk of high water is greatest from April to October. Normally, no work is allowed during this period. However, the monitoring platforms provide continuous, real-time insight into the dike’s flood safety. Daan says: “Monitoring gives us insight into, among other things, water levels on the Waal and pore water pressure in and beneath the dike. This means the effects of high water are immediately visible, giving us optimal risk management.”    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeFlood protection and climate-resilient water management
  • SubjectWater infrastructure
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.