Commissioned by the City of Amsterdam, the area in front of Amsterdam Central Station is being redeveloped. As a partner to main contractor Max Bögl, Beens Groep is delivering various elements of this complex infrastructure project. Beens Groep is a water engineering company operating nationwide and has been a specialist in structural water engineering and dredging for over 60 years. 

Karst-Jan Beens, managing director of Beens Groep, says: “Among other things, we are building new quays and temporary landing stages for the tour boats. The dredging work is being carried out by our subsidiary Beens Dredging. We are also installing the sheet-pile structure for the bicycle parking facility below the waterline. At the end of this large-scale project, we will install the permanent landing stages. It’s great that all of Beens Groep’s disciplines are involved in this project.”

Communication with all stakeholders is essential
Working in Amsterdam’s busiest area is a challenge, with large numbers of people, trams and vessels, as well as many stakeholders. Fred Groot, project manager for Wet Infrastructure, says: “It’s busy below the waterline too. The new Noord/Zuidlijn and numerous cables and pipelines run beneath it. This is a complex operation in which communication with all stakeholders is essential.” 

Beens Groep

From left to right: Gijs Methorst (operations manager, Beens Dredging), Fred Groot (project manager, Wet Infrastructure), Gert Beens (water engineering site manager), Karst-Jan Beens (managing director, Beens Groep).

Construction of new quay structures.

Gert Beens, water engineering site manager, explains that transporting equipment and materials past the low bridges is a complex operation. “Beens’s cranes are partly dismantled and transported to the site in sections on deck barges. This also meets the City of Amsterdam’s requirements.” Through its Amsterdam Vaart programme, the city aims to make urban logistics cleaner and smarter, including by exploring the potential of transporting construction materials by water. Gijs Methorst, operations manager at Beens Dredging, describes one of the challenges involved in the dredging work: “A large section of Prins Hendrikkade is being excavated, enlarging the Open Havenfront waterway. All the excavated soil has to be taken out of the city by water. It’s complicated, with all the other vessel traffic, but not impossible! It takes more than simply carrying out the work. Thinking through the issues and identifying opportunities and challenges for the project team as a whole: that’s where our strength lies.”

Beens Groep

The water engineering work is being carried out from the water.

Beens Groep

Temporary facilities had to be provided for the shipping companies so that the waterway would be clear for construction.

Reusing excavated soil
“We also look at how we can work as sustainably as possible. That’s something we always champion. In this project, for example, in addition to transporting construction materials by water, the soil is being reused on other nearby projects. This gives the enormous volume of excavated soil a useful new purpose.”

The brief is to keep the area functional while the work is under way and cause as little disruption as possible. “You don’t want to disrupt the city’s rhythm.” The success of the project as a whole depends on every aspect being perfectly coordinated. Everyone has their own responsibilities, but delivering the work successfully takes a collective effort. “Beens Groep is the partner that works collaboratively and contributes ideas, whether as part of a construction team or as a partner, and is involved from start to finish,” concludes Karst-Jan Beens.  

Beens Groep

It is a major challenge to transport all the excavated soil out of the city by water.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeFlood protection and climate-resilient water management
  • SubjectWater infrastructure
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.