Water infrastructure

Heavy sheet piles call for smart techniques

Zorgen voor minimale hinder is dan ook zeker één van de uitdagingen in het dijkversterkingsproject.
Zorgen voor minimale hinder is dan ook zeker één van de uitdagingen in het dijkversterkingsproject.

Gebr. De Koning takes on challenges on land and water. That mindset comes in handy on the Gorinchem–Waardenburg dike reinforcement project. Installing heavy steel structures up to 20 metres deep on mostly narrow dikes calls for smart solutions and techniques.

“The challenge is to use the techniques in a way that minimises disruption to the surrounding area,” says Leo van Dijk, commercial manager at Gebr. De Koning. “We’re in our element where land meets water. That could mean cofferdams, but also quay walls and dikes. Dike reinforcement is a perfect fit for what we do. Dike stability is vital. Dikes must not collapse during high water. To prevent this, we install very long sheet piles up to around 20 metres deep. This requires heavy equipment, which brings its own risks, such as severe vibration. Minimising disruption is therefore one of the key challenges on a dike reinforcement project. Fortunately, we enjoy a challenge. We’re at our best when things get complicated.”

Very long sheet piles are installed up to around 20 metres deep.

Smart techniques

Installing the heavy sheet piles requires the right equipment, as well as smart solutions and techniques. “We have several techniques for installing sheet piles, which we call our toolbox. Each technique has its pros and cons. The more tools in the box, the more options we have and the better we can match the method to the surroundings. That’s why we invest heavily in equipment and resources. For the dike reinforcement between Gorinchem and Waardenburg, we’re using several techniques, including high-frequency vibratory techniques and vibration-free methods such as silent piling and quattro piling.”

A model project

“Climate change and more extreme weather mean we need to be extra vigilant about high water. Our many years of expertise, experience and commitment in the fight against water help ensure that everyone can sleep soundly, without worrying about getting their feet wet. What makes this project special is the collaboration between the client and contractor. It is a flagship project and should become a model for how dike reinforcement is carried out in the future.”     

Question about this story? Ask your question

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeFlood protection and climate-resilient water management
  • SubjectWater infrastructure
  • CompanyGebr. De Koning
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.