Van Grinsven Grondboringen en Bronbemaling heeft op de verschillende locaties met de eigen ‘fabriek op wielen’ de benodigde filterbemalingen voorzien.
Van Grinsven Grondboringen en Bronbemaling heeft op de verschillende locaties met de eigen ‘fabriek op wielen’ de benodigde filterbemalingen voorzien.

To combat drought in the Peel region, more water is being brought into the area at the upstream end. To regulate this increased capacity downstream, a number of structures have been modified and refurbished. The project is part of the Optimisation of Water Supply to the Peel Canals programme. Van Grinsven Grondboringen en Bronbemaling has installed the necessary wellpoint dewatering systems at various locations using its own ‘factory on wheels’. 

The dewatering plan for modifying and refurbishing the structures already specified wellpoint dewatering, says Tom Jacops, co-owner of Van Grinsven Grondboringen en Bronbemaling. “Horizontal dewatering using drains was not possible because of the cables and pipes underground, and because the weirs are simply too compact for this technique. That left just one option: mechanically installing wellpoints. In the preparatory phase, we had already installed monitoring wells across the region for main contractor Vissers Ploegmakers to monitor groundwater levels. We used these readings to draw up the dewatering plan for each individual structure, enabling Vissers Ploegmakers to apply for the abstraction and discharge permits.”

Reducing flow rates

Van Grinsven Grondboringen en Bronbemaling worked with Vissers Ploegmakers to optimise the excavation support design at each location, so that the sheet piles would hold back a large proportion of the groundwater flows. “This allowed us to reduce the high flow rates of the water to be pumped as much as possible,” Tom explains. “There were a few deep excavations with particularly high flow rates. It was also sometimes quite a challenge to reach the sites with our equipment. Our jetting mast for installing the wellpoints is about 10 metres high, which meant we couldn’t position the wellpoints beneath the canopy of a tree. At some sites, we had to work out how to make everything fit.”

At the end of November 2023, Van Grinsven Grondboringen en Bronbemaling commissioned a new truck for drilling geothermal boreholes.

Factory on wheels

Van Grinsven Grondboringen en Bronbemaling is entirely self-sufficient on site. “We are well equipped for projects like these, where we have to provide dewatering at remote sites. Our truck is effectively a complete factory on wheels, equipped with a jetting pump, 10 m3 of process water and a crane.” The specialist from Wilbertoord recently added a fully electric machine for emission-free jetting and installation of wellpoint dewatering systems. “We listen to the market and are constantly working on new developments. For example, at the end of November 2023 we commissioned a new truck for drilling geothermal boreholes. The process is fully automated, with even greater precision and visibility.”

With three rigs now in operation, Van Grinsven Grondboringen en Bronbemaling has considerable expertise in installing geothermal boreholes. “We handle the entire process in-house, from the design and notification or permit application through to installing the manifold and pressure-testing the system with glycol. We also install deep drainage systems and drill irrigation wells and fire water wells. Few companies have such deep and broad expertise.”   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeUnderground construction
  • SubjectWater infrastructure
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.