Circular steel in a primary flood defence

Text Roel van Gils Image Maurits Peerbolte

Inmiddels is de bouwkuip opgeleverd en is Combinatie Waddenkwartier gestart met de bouw van de getijdenduiker.
Inmiddels is de bouwkuip opgeleverd en is Combinatie Waddenkwartier gestart met de bouw van de getijdenduiker.

The creation of the Marnewaard tidal area is one of three ecological enhancement projects being carried out as part of the Lauwersmeerdijk, Vierhuizergat dike reinforcement scheme. The work includes the construction of a tidal culvert through the primary flood defence. What makes the project truly unique is that the culvert is being built inside a cofferdam with walings and struts made from reclaimed steel. A first! This has been made possible by close collaboration between Heijmans Funderingstechnieken and Lommers Welding Service. 

The opening through the dike consists of a tidal culvert, which is being built inside a temporary cofferdam measuring 100 metres long and 12.6 metres wide. “During the preparatory phase, we suggested making the walings and strut frames from steel that had been used before and was in storage at our premises,” says Roy Kerkhof of Heijmans. “However, you cannot simply reuse steel if you strictly adhere to the applicable standards. This is particularly true when it forms part of a primary flood defence, where consequence class CC3 applies and the properties of the steel must be known. Together with Lommers, we began a research programme to find out whether we could upgrade the reclaimed steel and use it in the cofferdam for the primary flood defence. Lommers has the expertise, but is also willing to innovate.”

This project is typical of the comprehensive services offered by Lommers Welding Service.

Extensive testing

New steel is supplied with a certificate detailing, among other things, its technical properties. “With reclaimed steel, that information is sometimes no longer available, quite apart from the fact that the steel may have been through all sorts of things,” says Raymond Brand, welding coordinator at Lommers Welding Service. “Under the latest version of the NTA, it has been possible since 2023 to use reclaimed steel under these stringent standards, provided the client approves and it can be demonstrated that the steel meets the requirements and is therefore effectively equivalent to new steel. We first carried out a visual inspection of Heijmans’ reclaimed steel and made an initial selection. The steel quality and weldability were then tested using non-destructive and destructive testing. An external laboratory verified the mechanical properties for a second-line inspection. We compiled all this information in a document comparable to the original certificate, demonstrating that the donor steel meets the requirements.”

Execution class 3

Of the 200 tonnes of steel required for the walings and struts, more than 90% was reclaimed steel. The remaining 10% was new steel, as this amount was rejected during quality inspections and had to be replaced. Lommers also carried out all the welding on site to execution class 3, including the associated welding documentation. The cofferdam has now been handed over, and Combinatie Waddenkwartier has begun construction of the tidal culvert. The cofferdam will be dismantled in a year’s time. All the steel has been assembled and numbered so that it is traceable, both for this project and for circular use in a future project. This is one of the first projects in which reclaimed steel has been successfully upgraded for circular use on this scale and to these stringent standards. 

This is one of the first projects in which reclaimed steel has been successfully upgraded for circular use on this scale and to these stringent standards.

Innovation

This project is typical of the comprehensive services offered by Lommers Welding Service. “We work on many projects, both on site and in the workshop, where an execution class under NEN-EN 1090 and/or the ROK applies. We are happy to contribute during the preparatory phase to help deliver projects sustainably, and we are willing to innovate, even when it may not be the easiest route,” says Gerda Lommers. “In the years ahead, the infrastructure sector faces a huge replacement and renovation challenge. We take an integrated approach with our clients, working together to develop a robust design that can be built in practice. ‘Smart’ construction methods help us stay within the programme, project requirements and budget. That is truly unique for a steel engineering company. We continually develop our company and all our employees so that we can successfully take on all replacement and renovation challenges and future work.”     

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeFlood protection and climate-resilient water management
  • SubjectWater infrastructure
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.