Anchoring specialist takes delivery to an even higher level
Text Roel van Gils Images High 5 Solutions

How can the anchoring work for a dike reinforcement project be carried out more intelligently, efficiently and sustainably? Dijkalliantie Neder-Betuwe and anchoring specialist High 5 Solutions set out to answer that question together. Previous experience, including on the Tiel-Waardenburg dike reinforcement project, provided an important foundation.
“The lessons learned on that project have been taken to an even higher level here,” says Timo Gijbels of High 5 Solutions. “With this approach, we are increasingly becoming a long-term partner, working with clients to find the smartest and most efficient way to deliver a project.”
High 5 Solutions has gained extensive practical experience anchoring sheet piles on dike reinforcement projects. Even so, the current project is seen as a further step forward. This is not only because of its scale, a stretch of more than twenty kilometres with almost 2,000 anchors, but above all because it combines zero-emission working, smart logistics and the application of practical experience gained on previous projects.
As anchoring partner to Dijkalliantie Neder-Betuwe, High 5 Solutions has contributed specialist expertise in working platforms, anchor chair structures, logistics and delivery. Three key objectives guided the work: carrying out as much of the anchoring work as possible with zero emissions, creating safe working conditions, and standardising structural solutions as efficiently as possible to make on-site delivery as straightforward and efficient as possible.

Hybrid and zero-emission
The anchors are installed using large 55-tonne drilling rigs that can operate both on top of the dike (‘over the top’) and at its toe. The rigs currently run on HVO100 fuel, while support equipment, such as the auxiliary crane and grout mixing plant, is fully electric, powered by battery packs that circulate within the project.
“In time, a fully electric ‘over the top’ drilling rig will join the fleet, allowing us to carry out the entire anchoring scope with zero emissions,” says Timo. “This machine is currently being built and will make zero-emission sonic drilling possible on large-scale dike reinforcement projects.”
Improved ergonomics
Important progress has also been made in ergonomics. “Thanks to careful preparation, all the anchors are manufactured to size in advance and divided into sections that can be handled entirely by machine,” says Timo. “This means our employees no longer have to move short anchor sections by hand. This improvement stems directly from experience and discussions on previous projects.”
The same applies to the anchor chairs and the holes in the sheet piles. These have been standardised so that the same fittings and detailed dimensions can be used throughout. “This makes things simpler, increases production speed and prevents errors during installation,” says Timo.

Sonic drilling technology
High 5 Solutions uses its patented sonic drilling technology to install the anchors. “By vibrating at high frequency, we can drill more easily through hard soil layers. This reduces resistance and the amount of cement grout needed,” Timo explains. “The worksite also stays cleaner, as hardly any grout flows back to the ground surface. This benefits everyone who has to work there after drilling, from welders and groundworkers to the teams testing the anchors.”
The first thirty anchors have now been installed successfully. A larger part of the work will follow later this year, when hundreds of metres of sheet piles are anchored. Timo says everyone at High 5 Solutions is looking forward to contributing once again to a leading dike reinforcement project. “The fact that the project’s aim of installing as many anchors as possible with zero emissions is a perfect match for our own vision makes it all the more rewarding.”
“The excellent cooperation with Dijkalliantie Neder-Betuwe and the project suppliers for the anchor steel (TAB), anchor chairs (Ton van Leeuwen Snijwerken) and cement-based grout mortars (Weber Beamix) means we can work as one team and thoroughly enjoy what we do.”
Question about this story? Ask your question
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeFlood protection and climate-resilient water management
- SubjectWater infrastructure
- CompanyTon van Leeuwen Snijwerken