A critical, fresh perspective on risks

Werkzaamheden naast bebouwing.
Werkzaamheden naast bebouwing.

The Gorinchem-Waardenburg dike reinforcement project inevitably involves risks. It is therefore important to identify and monitor all potential risks. This is a responsibility that construction inspection firm BouwQ is ideally placed to take on. As an independent party, it is responsible for risk management on behalf of insurer Swiss Re.

‘This is a major project,’ says Benno Bruinsma, risk controller at BouwQ. ‘It is a very large dike reinforcement operation that will take several years. That makes the likelihood of damage occurring during the project very real. This could include excavation damage to cables and pipelines, cracks in homes caused by vibration and settlement, or even a sudden weakening of the existing dike. Damage, large or small, always causes some delay and therefore additional costs, as well as potential reputational damage and complaints from local residents. Everyone involved, including the contractors, insurers and local residents, therefore benefits from thorough, independent risk management focused specifically on this issue.’

Benno Bruinsma, risk controller at BouwQ.

Additional precautions required

BouwQ is a team of experienced, expert and independent engineers and inspectors committed to ensuring the safety and quality of structures through targeted inspections at every stage and across all aspects of construction projects and processes. It works not only for government and construction companies, but also for specialist engineering insurers. The latter is the case with the Gorinchem–Waardenburg dike reinforcement project. BouwQ is a Risk Control firm recognised by Dutch brokers and insurers. ‘Construction work in a vulnerable setting such as a dike reinforcement project requires additional precautions to prevent construction risks. Taking out adequate construction and liability insurance is standard practice, of course. Within the scope of the insurance, we assess all relevant risks during the design phase and check at critical points during construction that the necessary risk mitigation measures have been taken. We start by assessing the risks in the project plan, in what is known as the baseline report. We identify all major risks, as well as the control measures already planned by the contractor. Where necessary, we recommend additional measures. BouwQ then follows up on the risks identified in the baseline report during the construction phase, checking that all agreed measures are being implemented. Sometimes circumstances change and it turns out that the control measures are not sufficient to prevent damage. We discuss this with the parties as soon as possible.’ 

If BouwQ identifies a risk during an inspection, it discusses it with the contractor straight away.

High-water season

What happens if Bruinsma and his colleagues identify a risk? ‘The contractors are responsible for correctly preparing and implementing the agreed control measures. We are not on site every day, but we check every few weeks whether this is actually happening. If we identify a risk during an inspection, we discuss it with the contractor straight away. Sometimes there are good reasons for deviating from the plans. We then have to decide whether to notify the insurer of an increased risk. As an example of a risk associated with dike reinforcement, Bruinsma cites a high-water event during the work. ‘Autumn and winter are the high-water season, when this risk is greatest. This must be given careful consideration when planning and carrying out work on the existing dike.’ BouwQ analyses all the contractor’s plans and measures relating to this in detail.  

Buildings alongside the dike.

Working together

Although Bruinsma’s role as risk controller is to inspect and monitor, he sees added value in keeping all the parties involved on their toes. ‘There can sometimes be tension between the risks we identify and a contractor’s perspective, as control measures naturally cost money. On the other hand, we complement each other because, as an external party, we bring a fresh yet critical perspective. We often join a project that is already under way and spot risks that the project team has not yet noticed. In this way, we contribute to the work and offer advice on additional measures, drawing on our experience with similar projects. Ultimately, we all benefit from the dike reinforcement work progressing smoothly and without delay.’     

Have a business enquiry for BouwQ B.V.? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeFlood protection and climate-resilient water management
  • SubjectWater infrastructure
  • CompanyBouwQ B.V.
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.