The new year was ushered in with a celebratory official opening of the Leie works at and around the weir and lock complex…
The new year was ushered in last weekend with a celebratory official opening of the Leie works at and around the weir and lock complex in Harelbeke. Temporary Association (THV) Leieland, comprising contractors Jan De Nul nv, Herbosch-Kiere nv, Engie Fabricom nv and Aelterman bvba, was responsible for the design and delivery of the works.
Over the past five years, THV Leieland has worked on behalf of De Vlaamse Waterweg to renew and modernise the weir and lock, navigation channel and surrounding area along the Leie in Harelbeke.
Jan De Nul nv and Herbosch-Kiere nv were jointly responsible for the civil engineering works, as well as overall coordination and aligning the interests of all parties involved. Engie Fabricom nv carried out the electromechanical works, while Aelterman bvba was responsible for the steel structures. Their close collaboration led to an optimal design and high-quality delivery, in nautical, hydraulic, technical and aesthetic terms.
Working in an urban area
The infrastructure works took place in the heart of Harelbeke. The Leie also had to remain open to navigation throughout the works. These factors directly affected the construction methods and project schedule.
THV Leieland opted to build a temporary lock so that shipping would not be disrupted by the works. A temporary weir prevented flooding during construction.
The new lock and weir were planned for the same location as the old ones to achieve an optimal nautical and hydraulic design. In other words, construction could only begin once the temporary infrastructure was in place and the old infrastructure had been demolished.
Energy-neutral weir and lock complex
Alongside the new weir and lock complex, THV Leieland built a pumping station with two turbines. When there is surplus water, the turbines will generate electricity. Conversely, during dry periods and when water is in short supply, the pumping station can pump water into the upstream pound. The expected energy output exceeds the complex’s energy consumption, meaning it can be considered energy-neutral.
Seine Schelde project
The Leie works in Harelbeke form part of the wider Seine Schelde project, which will improve the navigable connection between the Seine and Scheldt basins. Following several large-scale infrastructure projects in France, Wallonia and Flanders, inland vessels of up to 4.500 tonnes will be able to travel between Paris and Antwerp. These works include the renewal of locks, weirs and quay walls, the deepening of existing canals or construction of new ones, and raising bridges.
Infrastructure works delivered by THV Leieland
Demolition of the old infrastructure
New lock (230m long, 12,5 m wide x 4,70m water depth)
New weir (2 weir gates, each 12,5m wide)
Pumping station with turbines
Fish pass
Quay walls (2 km)
Dredging works
Installation of the new steel Hogebrug (80m and 1.000 tonnes), Bloemmolenbrug (movable cycle bridge) and Banmolenbrug