BouwMat

THV Leieland completes Leie works in Harelbeke

THV Leieland completes Leie works in Harelbeke

The New Year was ushered in with a festive official opening of the Leie works at and around the weir and lock complex…

The New Year was ushered in last weekend with a festive official opening of the Leie works at and around the weir and lock complex in Harelbeke. The temporary partnership (THV) Leieland, comprising contractors Jan De Nul nv, Herbosch-Kiere nv, Engie Fabricom nv and Aelterman bvba, was responsible for the design and delivery of the works.

Over the past five years, THV Leieland has worked on behalf of De Vlaamse Waterweg to renew and modernise the weir and lock, navigation channel and the area along the Leie in Harelbeke.

Jan De Nul nv and Herbosch-Kiere nv were jointly responsible for the civil engineering works, as well as overall coordination and reconciling the interests of all parties involved. Engie Fabricom nv carried out the electromechanical works, while Aelterman bvba was responsible for the steelwork. Their close collaboration resulted in an optimal design and high-quality delivery in nautical, hydraulic, technical and aesthetic terms.

Working in an urban area

The infrastructure works took place in the heart of Harelbeke. The Leie also had to remain open to navigation throughout the works. Both factors had a direct impact on the construction methods and project schedule.

THV Leieland opted to build a temporary lock, ensuring that the works did not disrupt shipping. A temporary weir prevented flooding during the works.

The new lock and weir were planned for the same location as the old ones to achieve an optimal nautical and hydraulic design. In other words, construction could only begin once the temporary infrastructure was in place and the old infrastructure had been demolished.

Energy-neutral weir and lock complex

Alongside the new weir and lock complex, THV Leieland built a pumping station with two turbines. The turbines will generate energy when there is excess water. Conversely, during dry periods and water shortages, the pumping station can pump water into the upstream reach. The expected energy output exceeds the complex’s consumption, meaning the weir and lock complex is considered energy-neutral.

Seine Scheldt project

The Leie works in Harelbeke form part of the wider Seine Scheldt project, which improves the waterway link between the Seine and Scheldt basins. Thanks to several large-scale infrastructure projects in France, Wallonia and Flanders, inland vessels of up to 4,500 tonnes will be able to travel between Paris and Antwerp. These projects include the renewal of locks, weirs and quay walls, the deepening of existing canals or the construction of new ones, and the raising of bridges.

Infrastructure works carried out by THV Leieland

  • Demolition of old infrastructure
  • New lock (230m long, 12.5 m wide x 4.70m water depth)
  • New weir (2 weir gates, each 12.5m wide)
  • Pumping station with turbines
  • Fish pass
  • Quay walls (2 km)
  • Dredging
  • Installation of new steel Hogebrug (80m and 1,000 tonnes), Bloemmolenbrug (movable cycle bridge) and Banmolenbrug
  • Sewerage, district heating network and roads

Question about this story? Ask your question

Who worked on Leiewerken

  1. contractorJan De Nul nvIn this story
  2. contractorHerbosch-Kiere nvIn this story
  3. steel construction worksAelterman bvbaIn this story
  4. electromechanical worksEngie Fabricom nvMentioned in THV Leieland completes Leie works in Harelbeke

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectLeiewerken
  • SubjectBouwMat
  • CompanyJan De Nul nv
  • CompanyHerbosch-Kiere nv
  • CompanyAelterman bvba
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.