The new year got off to a celebratory start last weekend with the official opening of the Leie works at and around the weir and lock complex in Harelbeke. The temporary partnership (THV) Leieland, comprising contractors Jan De Nul nv, Herbosch-Kiere nv, Engie Fabricom nv and Aelterman bvba, was responsible for the design and delivery of the works.
Over the past five years, THV Leieland has worked on behalf of De Vlaamse Waterweg to renew and modernise the weir and lock, waterway and surrounding area along the Leie in Harelbeke.
Jan De Nul nv and Herbosch-Kiere nv were jointly responsible for the civil engineering works, as well as overall coordination and balancing the interests of all parties involved. Engie Fabricom nv was responsible for the electromechanical works, and Aelterman bvba for the steelwork. Their close collaboration resulted in an optimised design and high-quality delivery, in nautical, hydraulic, technical and aesthetic terms.
Working in an urban area
The infrastructure works were carried out in the heart of Harelbeke. The Leie also had to remain open to navigation throughout the works. All this had a direct impact on construction methods and project planning.
THV Leieland opted to build a temporary lock, ensuring that navigation was not disrupted by the works. A temporary weir prevented flooding during the works.
The new lock and weir were planned for the same location as the old ones to achieve an optimal nautical and hydraulic design. In other words, construction could only begin after the temporary infrastructure had been installed and the old infrastructure demolished.
Energy-neutral weir and lock complex
Alongside the new weir and lock complex, THV Leieland built a pumping station with two turbines. When there is excess water, the turbines will generate energy. Conversely, during dry periods and when water is in short supply, the pumping station can pump water to the upstream reach. The expected energy output exceeds the complex’s energy consumption, making it energy-neutral.
Seine Schelde project
The Leie works in Harelbeke form part of the wider Seine Schelde project, which improves the waterway connection between the Seine and Scheldt basins. Following major infrastructure works in France, Wallonia and Flanders, inland vessels of up to 4,500 tonnes will be able to travel between Paris and Antwerp. These works include the renewal of locks, weirs and quay walls, the deepening of existing canals or construction of new ones, and the raising of bridges.
Infrastructure works delivered by THV Leieland
Demolition of old infrastructure
New lock (230m long, 12.5 m wide x 4.70m water depth)
New weir (2 weir gates, each 12.5m wide)
Pumping station with turbines
Fish pass
Quay walls (2 km)
Dredging
Installation of new steel Hogebrug (80m and 1,000 tonnes), Bloemmolenbrug (movable cycle bridge) and Banmolenbrug