Today, State Secretary for Infrastructure and Water Management Stientje van Veldhoven opened the first circular concrete viaduct in the Netherlands. She did so on the first day of Circular Economy Week. The viaduct was recently installed near Kampen and is an initiative by Rijkswaterstaat, contractor Van Hattum en Blankevoort (VolkerWessels) and precast concrete specialist Consolis Spanbeton.

Circular is the future
We have only one planet, Van Veldhoven emphasised in her speech. “And its resources are not infinite: we have to make do with what we have here. Reusing materials is the future. It also helps us meet this government’s climate targets. From now on, our raw materials will come not from an oil barrel, but from the rubbish bin.”

First circular viaduct
The deck of the circular viaduct consists of 40 concrete elements and can be completely dismantled without damage, moved and rebuilt at a new location. “This means there is no waste, no new raw materials are needed, and used materials can be reused to the highest possible standard,” says Esther van Eijk of Van Hattum en Blankevoort. “Where conventional viaducts are demolished after 30 to 50 years, the circular viaduct has a service life of 200 years, around 6 times as long. It is the first concrete viaduct in the Netherlands to be built this way.”

Innovative design
A range of circular principles have been applied in the viaduct’s innovative design. “One notable feature is that the elements interlock like ‘LEGO bricks’ using lugs, that the prestressing cables are not cast in, and that the joints between the concrete elements can be detached,” explains Kees Quartel of Consolis Spanbeton. “This means the elements do not have to be demolished when the viaduct is dismantled, and can be reused undamaged. Using elements also makes it possible to build new viaducts with the same ‘building blocks’, varying in length and width.”

Testing the circular viaduct
Over the coming months, the three project partners will test the first prototype of the circular viaduct on a construction site between Kampen and Dronten. The site is being used for construction of the Reevesluis, part of the Ruimte voor de Rivier IJsseldelta project. Construction traffic uses the viaduct. Extensive monitoring is being carried out to assess how the viaduct performs. The test data will inform further development of the circular viaduct.

Launching a learning environment for circular viaducts
To enable the large-scale use of circular viaducts, Rijkswaterstaat is creating a learning environment with Van Hattum en Blankevoort and the Bouwcampus. Its launch meeting took place immediately after the opening of the circular viaduct. Rijkswaterstaat Director-General Blom explains: “The learning environment brings together the knowledge currently available to clients, infrastructure companies and knowledge institutions. The aim is to agree on shared principles for further developing the concepts currently on the market. We urge civil engineering contractors and road authorities with good ideas of their own to join us and contribute to the development of the circular viaduct.”

Working together as equal partners
Within the partnership and the learning environment, Rijkswaterstaat is acting as a ‘launching customer’, seeking to drive change. It is doing so by supporting companies as they further develop a shared concept. Director-General Blom says: “To accelerate circular innovation, Rijkswaterstaat wants to be involved earlier and more closely in its development. Collaboration between equal partners across the entire supply chain is essential to making fully circular construction possible.”

Circular construction by 2030
By building the Netherlands’ first circular viaduct, the three partners are making an innovative contribution to the sustainability ambitions of Rijkswaterstaat and the Netherlands: a 49% reduction in CO2 emissions (compared with 1990) and circular construction by 2030.

Question about this story? Ask your question

Who worked on it

Rijkswaterstaat Kampen viaduct in Kampen

  1. initiativeRijkswaterstaat
  2. contractorVan Hattum en Blankevoort
  3. prefabrication contractorConsolis Spanbeton

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectRijkswaterstaat Kampen viaduct
  • ThemeExtending the life of roads and civil engineering structures
  • SubjectSpecials
  • CompanyRijkswaterstaat
  • CompanyVan Hattum en Blankevoort
  • CompanyConsolis Spanbeton
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.