Monitoring the historic Hunsingosluis
Text Roel van Gils Image Unihorn

Building next to a listed monument is always challenging, especially when it is founded on ‘unusual’ ground. This prompted Strukton to keep a particularly close eye on the Hunsingosluis, built in 1859, during construction of the new pumping station as part of the Nieuwe Waterwerken Zoutkamp project. Unihorn, part of Strukton, was brought in to carry out extensive monitoring work.
“The Hunsingosluis is a historic structure, built of masonry on timber piles with pile caps and founded on the first sand layer,” explains Remo Hofland of Unihorn. “Below that sand layer is a layer of old pot clay, which has a tendency to swell when the surcharge above it is removed. This could cause deformation and even rotation of the old lock in any direction. That could compromise the lock’s stability during the works. Monitoring during construction is therefore essential, both to prevent this and to allow timely control measures to be taken in an ‘emergency’.”

Total stations and vibration sensors
Unihorn therefore installed a total station on top of the lock on each side of the lock chamber walls. The instruments automatically take readings at fixed points in the surrounding area 24/7. “The data are collected so that any deformation of the lock chamber walls can be detected at an early stage. If a threshold is at risk of being exceeded, all the alarm bells ring and work is stopped so that control measures can be taken. Fortunately, that was not necessary here,” says Remo, explaining that the total stations have since been removed because the works have moved on to the next phase and can no longer cause deformation of the old lock. Unihorn’s automatic vibration sensors are still in place at the site, however. “We will also continue to inspect the lock manually at regular intervals.”
Unihorn is an independent research, consultancy and design firm specialising in the niche fields of pavement investigations, conditioning studies and asset management. “We also produce 3D designs for public spaces, roads and dykes, carry out environmental investigations and have our own accredited laboratory for analyses. Finally, we are very active in geodata and monitoring, as here in Zoutkamp. We also carried out crack-width measurements at the Hunsingosluis at an earlier stage to monitor any changes in existing cracks.”
A business enquiry for Unihorn? Get in touch
Who worked on Waterwerken Zoutkamp
- water boardWaterschap NoorderzijlvestMentioned in Zoutkamp pumping station is also ‘nature-inclusive’
- restoration of the listed sectionKoninklijke Oosterhof HolmanMentioned in Restoration of Hunsingosluis is a true craft
- Pumping station pumps
Stork PompenMentioned in One of the world’s largest fish-friendly submersible pumps