Huge lattice girders crucial to construction phasing

De inzet van de zwaarste mobiele kraan (750 ton) was een vereiste om de vakwerkspanten in te hijsen.
De inzet van de zwaarste mobiele kraan (750 ton) was een vereiste om de vakwerkspanten in te hijsen.

To allow the construction pits for the Maasdeltatunnel approach roads to be excavated in phases, VDS Rotterdam designed, manufactured and installed three huge lattice girders on site, on behalf of BAAK.

The tender requirements specified that the girders would be subject only to compressive loads, but an additional dimension emerged during the project in the form of tensile loading. 

“We submitted a proposal for the design of the lattice girders through the tender process more than a year and a half ago,” says Ronald de Koning, project coordinator at VDS Rotterdam. “Our bid proved to be the most economically advantageous design. The specified forces led to the development of a lattice frame. In total, there are three lattice girders, made from HEB1000/900 sections for the longitudinal members and HEB700/500/300 sections for the braces. The materials used are grade S355, and each girder weighs 220 tonnes. Two girders are now in use on the south side and one frame on the north side.”

The girders make it possible to divide the construction pits into compartments, allowing construction consortium BAAK to carry out excavation and propping work in phases.

Upper and lower girders

The girders make it possible to divide the construction pits into compartments, allowing construction consortium BAAK to carry out excavation and propping work in phases. “This ultimately saves time in both planning and execution,” says De Koning. “The lattice girders are positioned against an end wall and transfer the forces generated there by underwater excavation to the longitudinal walers. The three lattice girders are almost identical in size, measuring 39 metres long and 9 metres wide. In our factory, each girder was assembled as an upper section (130 tonnes) and a lower section (90 tonnes), each comprising 2 layers of HEB sections connected by splice plates. The maximum load of 120 tonnes that could be handled was determined by the lifting distances from the construction pit to its edge, and the lifting height. Using the heaviest mobile crane available, rated at 750 tonnes, was therefore essential. Even so, this was much more cost-effective than the alternative of a crawler crane assembled on site. At the site, the upper and lower sections were joined with the longitudinal walers running across the combined walls to form a single structure.”

“Initially, the plan was to weld the girders to the combined wall,” says De Koning. “The girders would be subject only to compressive loads. The construction phasing was changed during the project, meaning the frame could also be subject to tension. In response, we developed a pivoting structure that was positioned against the combined wall and allows the girder to rotate.” VDS has now installed all three lattice girders. The company has considerable expertise in this area, both in engineering and execution. “In that respect, we’re a one-stop shop, covering the whole package from the drawing board through to installation on site. We’re also centrally located on the water. Transporting structures of this size is no problem for us.”     

Question about this story? Ask your question

Who worked on Maasdeltatunnel

  1. ImmersionStruktonMentioned in A-team to carry out the Netherlands’ largest tunnel immersion operation
  2. ImmersionDEME Infra Marine Contractors (DIMCO)Mentioned in A-team to carry out the Netherlands’ largest tunnel immersion operation
  3. main contractor consortiumBAAKMentioned in A-team to carry out the Netherlands’ largest tunnel immersion operation
  4. anchor pile systemGeotech MetalsMentioned in A stable foundation thanks to 3,130 grout-injection anchor piles
  5. roof trussesVDS RotterdamIn this story
  6. main supplierDYWIDAGMentioned in Longitudinal and transverse prestressing for the Maasdeltatunnel
  7. dewateringHenk van Tongeren Water & TechniekMentioned in Dewatering in all its forms
  8. construction consortiumBAAK construction consortiumMentioned in Dewatering in all its forms

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectMaasdeltatunnel
  • SubjectSpecials
  • CompanyVDS Rotterdam
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.