A-team to carry out the Netherlands’ largest tunnel immersion operation

The immersion of the two elements of the Maasdeltatunnel, part of the Blankenburgverbinding, is sure to go down in the history books. Never before in the history of Dutch immersed tunnels have such large elements been immersed. The operation is also taking place in fast-flowing water in one of the busiest areas of the Port of Rotterdam. It is only natural, then, to bring in the A-team.
The Maasdeltatunnel will consist of two elements, each 200 metres long, 42 metres wide and 8 metres high, which will be immersed one after the other in the Nieuwe Waterweg. Both elements are being built in a construction dock at the tunnel approaches, one on the south bank and the other on the north bank. The A-team will then take care of floating, transporting and immersing both tunnel elements. A-team is a joint venture between DEME Infra Marine Contractors (DIMCO) and Strukton Immersion Projects, both renowned for their extensive track records in tunnel immersion.

Unusual design
“We are joining forces for this challenging immersion operation,” says Eelco van Putten of DIMCO. “We actually have a dual role in the project. We are part of the BAAK main contractor consortium and, together with Strukton Immersion Projects, are responsible for the immersion.” The tunnel elements exist only on paper for now. Work is currently under way to build the approaches to the Maasdeltatunnel, which lies 30 metres below ground. “The approaches will be sealed off from the Nieuwe Waterweg by a double bulkhead,” explains Robbert Martens of Strukton Immersion Projects. “The construction dock will then be drained, and BAAK will start building the two elements, which will be ready in two years.” Van Putten adds that the elements’ design differs from that of typical Dutch immersed tunnels. “The ballast concrete is integrated into the immersion design and incorporated in ducts alongside the carriageway. This reduces the draught: the tunnel is wider and lower than is ‘customary’.”
Immersion operation
Once completed, the tunnel elements will be fitted with ballast tanks and sealed at the ends with steel panels. Martens: “The ballast tanks will then be filled with water, as will the construction dock. We will check that the floating process works as planned by emptying the ballast tanks. If everything goes well, we will fill the ballast tanks again and remove the double bulkhead from the approach. We will float the element off the dock floor once more, use a single high-water wave to tow it out of the dock, and position it in a controlled manner on the bed of the Nieuwe Waterweg within the same 24 hours.” Van Putten: “What is unique about the immersed tunnel design submitted at tender stage is that the port only needs to be closed on two Sundays. This design solution was rewarded at tender stage. The southern element will be positioned first, followed by the northern one two weeks later, again on a Sunday. We need that time to mobilise the immersion pontoons at the new element. In addition, current conditions are favourable at those times because of neap tide.”

Both tunnel elements will be immersed in an immersion trench, leaving a 2-metre gap between the last element and the approach. “The gap will be closed with a closure joint,” says Martens. “We will install steel formwork panels around the opening so that BAAK can carry out the concrete work. The immersion trench will then be backfilled, and a protective stone layer will be laid over the elements to protect the tunnel from falling or dragging anchors.”
“An exceptionally good working relationship has already developed, enabling us to deliver an outstanding performance at this design stage. The final immersion of these elements will be carried out to specification, down to the smallest detail, on the basis of the mutual trust we have built and our close collaboration.”
A business enquiry for Strukton Civiel? Get in touch
Who worked on Maasdeltatunnel
- ImmersionDEME Infra Marine Contractors (DIMCO)In this story
- main contractor consortiumBAAKIn this story
- anchor pile systemGeotech MetalsMentioned in A stable foundation thanks to 3,130 grout-injection anchor piles
Keep following this
Get an email when a new story is published. No account needed.
- ProjectMaasdeltatunnel
- SubjectBridge construction
- CompanyStrukton Civiel
- CompanyDEME Infra Marine Contractors (DIMCO)
- CompanyBAAK