Underground infrastructure

A stable foundation thanks to 3,130 grout-injection anchor piles

Het fundament van de toerit aan de noordzijde is gelegd door Jetmix met zijn specifieke, zelborende grout(injectie)ankerpalen, die hogere krachten kunnen opnemen dan de GEWI-ankers aan de zuidzijde.
Het fundament van de toerit aan de noordzijde is gelegd door Jetmix met zijn specifieke, zelborende grout(injectie)ankerpalen, die hogere krachten kunnen opnemen dan de GEWI-ankers aan de zuidzijde.

To provide access to the Maasdeltatunnel, which is being lowered onto the bed of the Scheur at a depth of around 26 metres, an approach road is being built on each side.

The foundation for the approach road on the north side was laid by Jetmix using its specialist self-drilling grout-injection anchor piles, which can take higher loads than the GEWI anchors on the south side.

Jetmix installed no fewer than 3,130 anchor piles along a 500-metre stretch, equivalent to 159 kilometres of drilling. “The approach road is being built as an embankment with a gradient of 4%,” explains Edwin Giljam, operations manager at Jetmix. “We installed the anchor piles at increasing depths below ground level, creating clear space for excavating the construction pit. At the deepest point, we reached a depth of minus 63 metres NAP (!), with the drill rods disconnected at minus 28 metres NAP, the depth to which the pit is being excavated.”

Jetmix spent around one year working full time to install the 3,130 anchor piles using five of its own KLEMM 807 drilling rigs.

Jetmix anchor pile system

The self-drilling grout-injection anchor pile system was developed by Jetmix. The system is manufactured by Geotech Metals. “For the Blankenburgverbinding, we used several versions of the grout-injection anchor pile system, with diameters of 82.5, 101.6 and 114.3 millimetres and varying wall thicknesses ranging from 12.5 to 28 millimetres. The pile system essentially consists of 6-metre sections of hollow pipe, threaded on the outside, with a drill bit at the end. We feed the grout mixture to the drill bit through a rod inside the hollow pipe. The mixture lubricates the drill bit and carries the material back up through the pipe. Because of ammonium acid contamination in the ground, once the required depth has been reached, the borehole is filled with a mixture using a different mixing ratio that is more resistant to ingress. The extension rods are then disconnected from the anchor pile system via a bayonet coupling and pulled back up.”

When the construction pit is excavated, a plate assembly is fitted to the Jetmix pile system to connect it to the underwater concrete that will be installed later. Giljam: “In its final configuration, our pile system can therefore withstand both tension and compression. We spent around one year working full time to install the 3,130 anchor piles. We used five of our own KLEMM 807 drilling rigs. The final pile was installed just before the 2020 construction holiday. Looking back, it was an intensive but highly efficient project. This was due in no small part to the dedicated logistics centre we set up on site.”     

Question about this story? Ask your question

Who worked on Maasdeltatunnel

  1. ImmersionStruktonMentioned in A-team to carry out the Netherlands’ largest tunnel immersion operation
  2. ImmersionDEME Infra Marine Contractors (DIMCO)Mentioned in A-team to carry out the Netherlands’ largest tunnel immersion operation
  3. main contractor consortiumBAAKMentioned in A-team to carry out the Netherlands’ largest tunnel immersion operation
  4. anchor pile systemGeotech MetalsIn this story
  5. roof trussesVDS RotterdamMentioned in Huge lattice girders crucial to construction phasing
  6. main supplierDYWIDAGMentioned in Longitudinal and transverse prestressing for the Maasdeltatunnel
  7. dewateringHenk van Tongeren Water & TechniekMentioned in Dewatering in all its forms
  8. construction consortiumBAAK construction consortiumMentioned in Dewatering in all its forms

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectMaasdeltatunnel
  • ThemeMaterials and techniques for infrastructure
  • SubjectUnderground infrastructure
  • CompanyGeotech Metals
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.