Building and installing the Jan Linzel Viaduct over the A4: a large-scale precision operation

Work on the bicycle viaduct in The Hague is nearing completion. The viaduct crosses the A4 between the Ypenburg and Prins Clausplein interchanges. The bicycle viaduct, known as the Jan Linzel Viaduct, is no less than 330 metres long.
Development
Because of its length, the viaduct consists of nine sections. These steel structures were fabricated by Hillebrand and will rest on eight concrete supports installed by Dura Vermeer. “It’s a very intensive project. We had to set up the entire engineering and production process in a relatively short period, with the closure of the A4 as an absolute deadline,” says Willie Lievense, project manager at Hillebrand. Installing the four sections above the A4 required thorough preparation, which Hillebrand’s several teams worked on carefully for a long time. “Good preparation is half the battle. Especially when you see how smoothly the main contractor, Dura Vermeer, and us, as a bridge-building specialist, work together. When you complement each other, make the most of each other’s strengths and appreciate each other’s added value, you achieve great results.”

Installing the viaduct sections was a major undertaking: no fewer than 4 of Mammoet’s 7 ‘heavyweights’ were working at the same time. This included a 750-tonne crane, the largest mobile crane on wheels that is still permitted on the road.
Production
Alongside the excellent collaboration with Dura Vermeer, Lievense also praises the entire Hillebrand team that worked on the project. Hillebrand has two large production facilities by the water, providing the capacity required for the job. “Production alone involved no fewer than 35,000 man-hours. The main challenge was creating the gently curved shape.” Lievense explains: “You have to take factors such as the bridge’s own weight, gravity and pressure loads into account, so during production you have to build in more curvature than you ultimately want. That takes a great deal of engineering.” The workshops in Middelburg and Vlissingen worked with a large jig, 54 metres long. Using this jig, they formed a kind of box structure from skin plates with internal stiffeners. “It might look like a matter of welding plates together, but it takes considerable know-how and experience to create a strong structure.”

Transport
“Transporting all these unusual sections and components was also a major challenge. Our partner Mammoet played an important role in this. Together, we explored all kinds of options. In the end, we decided to use heavy cranes to lift the enormous components onto an inland vessel in Middelburg and Vlissingen and transport them to Schiedam. There, the components were lifted off the vessel and driven to The Hague at night on special transport trailers. Our people were ready at the destination to assemble the bridge sections.”

And, of course, installation
Sections A and B were installed over the motorway carriageway on the first night. On the second night, the two largest sections, spanning the motorway’s entry and exit lanes, were installed: bridge section C, 54 metres long and weighing 160 tonnes, and bridge section D, 46 metres long and weighing 130 tonnes. “That kind of weight calls for heavy equipment,” says Lievense. “So four heavy-duty mobile hydraulic telescopic cranes were deployed: one 500-tonne, one 700-tonne and two 750-tonne cranes. It was a large-scale precision operation. When everything literally falls into place and the work is completed safely, it’s an immensely satisfying feeling.” The remaining five sections run alongside the motorway and will be installed in the final phase. Dura Vermeer will then, of course, complete the bridge.
Question about this story? Ask your question
Who worked on Jan Linzelviaduct
- main contractorDura VermeerMentioned in Building and installing the Jan Linzel viaduct over the A4: a precision operation on a grand scale
- steel structuresHillebrandMentioned in Building and installing the Jan Linzel Viaduct over the A4: a large-scale precision operation
- heavy-duty cranesMammoetIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectJan Linzelviaduct
- ThemeExtending the life of roads and civil engineering structures
- SubjectSpecials
- CompanyMammoet