Building and installing the Jan Linzel Viaduct over the A4: a large-scale precision operation

Work on the cycle bridge in The Hague is nearing completion. The bridge crosses the A4 between the Ypenburg and Prins Clausplein interchanges. The cycle bridge, known as the Jan Linzel Viaduct, is no less than 330 metres long.
Development
Because of its length, the bridge consists of nine sections. These steel structures were manufactured by Hillebrand and will rest on eight concrete supports installed by Dura Vermeer. “It’s a very intensive project. We had to set up the entire engineering and production process in a relatively short period, with the closure of the A4 as our absolute deadline,” says Willie Lievense, project manager at Hillebrand. Laying the four sections over the A4 required thorough preparation, which Hillebrand’s teams worked on carefully for a long time. “Good preparation is half the battle, especially when you have a smooth working relationship between main contractor Dura Vermeer and us as a bridge-building specialist. When you complement each other, play to each other’s strengths and value each other’s contribution, you achieve excellent results.”

Installing the bridge sections was a major undertaking: no fewer than 4 of Mammoet’s 7 ‘heavyweights’ were working at the same time. These included a 750-tonne crane, the largest mobile crane on wheels still permitted on the road.
Production
As well as praising the excellent collaboration with Dura Vermeer, Lievense commends the entire Hillebrand team that worked on the project. Hillebrand has two large production facilities on the water, providing the capacity required for the project. “Production alone involved no less than 35,000 man-hours. The main challenge was creating the slightly curved shape.” Lievense explains: “You have to account for factors such as the bridge’s own weight, gravity and load pressure, so during production you have to create a greater camber than the one you ultimately want. That takes a lot of engineering.” The workshops in Middelburg and Vlissingen worked with a large 54-metre-long mould. Using this mould, they created a kind of box girder from skin plates with internal stiffeners. “It might look like a matter of welding plates together, but it takes a great deal of know-how and experience to create a strong structure.”

Transport
“Transporting all these unusual sections and components was also a major challenge. Our partner Mammoet played an important role in this. Together, we explored all kinds of options. In the end, we decided to use heavy cranes to lift the enormous components onto an inland vessel in Middelburg and Vlissingen, then transport them by water to Schiedam. There, the components were lifted off the vessel and driven to The Hague at night on specialist transport trailers. Our team was ready at the destination to assemble the bridge sections.”

And, of course, installation
Sections A and B were installed above the motorway carriageway on the first night. On the second night, the two largest sections spanning the motorway’s entry and exit lanes were installed: bridge section C, 54 metres long and weighing 160 tonnes, and bridge section D, 46 metres long and weighing 130 tonnes. “That sort of weight calls for heavy equipment,” says Lievense. “So we deployed four heavy-duty mobile hydraulic telescopic cranes: one 500-tonne crane, one 700-tonne crane and two 750-tonne cranes. It was a large-scale precision operation. When everything falls into place, quite literally, and goes smoothly and safely, it’s an immensely satisfying feeling.” The remaining five sections run alongside the motorway and will be installed in the final phase. Dura Vermeer will then, of course, complete the bridge.
Question about this story? Ask your question
Who worked on Jan Linzelviaduct
- main contractorDura VermeerMentioned in Building and installing the Jan Linzel viaduct over the A4: a precision operation on a grand scale
- steel structuresHillebrandIn this story
- heavy-duty cranesMammoetMentioned in Building and installing the Jan Linzel Viaduct over the A4: a large-scale precision operation
Keep following this
Get an email when a new story is published. No account needed.
- ProjectJan Linzelviaduct
- ThemeExtending the life of roads and civil engineering structures
- SubjectBouwMat
- CompanyHillebrand