Work on the cycle viaduct in The Hague is nearing completion. The viaduct crosses the A4 between the Ypenburg and Prins Clausplein interchanges. The cycle viaduct, named the Jan Linzelviaduct, is no less than 330 metres long. 

Development

Because of its length, the viaduct consists of nine sections. These were fabricated in steel by Hillebrand and will rest on eight concrete supports installed by Dura Vermeer. “It’s a very intensive project. The entire engineering and production process had to be set up in a relatively short period, with the closure of the A4 as the absolute deadline,” says Willie Lievense, project manager at Hillebrand. Laying the four sections over the A4 in position required thorough preparation, which Hillebrand’s teams worked on carefully for a long time. “Good preparation is half the battle. That’s especially true when you see how smoothly the main contractor, Dura Vermeer, and we, as a bridge-building specialist, work together. When you complement each other, bring out the best in each other and value each other’s contribution, you achieve wonderful results.”

Installing the viaduct sections was quite a job: no fewer than 4 of Mammoet’s 7 ‘heavyweights’ were working at the same time, including a 750-tonne crane, the largest mobile crane on wheels that is still allowed on the road.

Production

As well as the excellent collaboration with Dura Vermeer, Lievense praises the entire Hillebrand team that worked on the project. Hillebrand has two large waterside production facilities, which provided the capacity needed for the project. “Production alone involved no fewer than 35,000 man-hours. The main challenge was creating the slightly curved shape.” Lievense explains: “You have to take factors such as the bridge’s own weight, gravity and pressure loads into account, so during production you have to create a greater camber than the one you ultimately want. That takes a great deal of engineering.” The workshops in Middelburg and Vlissingen worked with a large 54-metre-long jig. This jig was used to create a kind of box girder from steel plates, with internal stiffeners. “It may look like a matter of welding plates together, but it takes a great deal of know-how and experience to create a strong structure.”

Transport

“Transporting all these unusual sections and large components was also a major challenge. Our partner Mammoet played an important role in this. Together, we explored all kinds of options. In the end, we decided to use heavy cranes to lift the enormous components onto an inland vessel in Middelburg and Vlissingen, then transport them by water to Schiedam. There, the components were lifted off the vessel and driven to The Hague overnight on special transport trailers. Our people were ready at the destination to assemble the bridge sections.”

And finally, installation

Sections A and B were installed over the motorway carriageway on the first night. The following night, the two largest sections, which span the motorway’s entrance and exit lanes, were installed: bridge section C, measuring 54 metres and weighing 160 tonnes, and bridge section D, measuring 46 metres and weighing 130 tonnes. “That kind of weight calls for heavy equipment,” says Lievense. “So four heavy-duty mobile hydraulic telescopic cranes were deployed: one 500-tonne, one 700-tonne and two 750-tonne cranes. It was a precision operation on a grand scale. When everything literally falls into place and the work is completed safely, it gives you an immensely satisfying feeling.” The remaining five sections run alongside the motorway and will be installed in the final phase. Dura Vermeer will then, of course, complete the bridge. 

Question about this story? Ask your question

Who worked on Jan Linzelviaduct

  1. main contractorDura VermeerIn this story
  2. steel structuresHillebrandMentioned in Building and installing the Jan Linzel Viaduct over the A4: a large-scale precision operation
  3. heavy-duty cranesMammoetMentioned in Building and installing the Jan Linzel Viaduct over the A4: a large-scale precision operation

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectJan Linzelviaduct
  • ThemeExtending the life of roads and civil engineering structures
  • SubjectBouwMat
  • CompanyDura Vermeer
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.