Road construction

Substructure for Theemsweg route complete

De twee troggen die gebouwd werden mogen geclassificeerd worden als een moeilijke constructie.
De twee troggen die gebouwd werden mogen geclassificeerd worden als een moeilijke constructie.

In the Port of Rotterdam, the Havenspoorlijn, the first section of the Betuweroute, is being rerouted. The new section of track, more than 4 kilometres long and known as the Theemsweg route, is due for completion at the end of 2021. It will resolve the capacity bottleneck at the Calandbrug near Rozenburg. The new route runs over an elevated railway viaduct. Two arch bridges have been built along the route, which reconnects to the existing railway near the A15. Rerouting the line means that increasing rail traffic will no longer conflict with shipping, improving traffic flow.

The bridge near the lock in an atmospheric setting.

We spoke to Rik van Opdorp, project manager at Mobilis. “The substructure for the Theemsweg route, comprising the railway viaduct and modifications to the road network, was built by the SaVe contractor consortium, made up of TBI company Mobilis, Besix, Dura Vermeer, Hollandia and Iemants. As technical manager, I was responsible for overseeing the design and construction preparation, as well as day-to-day management. We were in close contact with the client, Port of Rotterdam Authority. The focus of this project was on engineering and safety.”

Rik van Opdorp, Project Manager at Mobilis

Numerous challenges and specialist expertise

The substructure for the Theemsweg route presented its share of challenges, Rik notes. “The project was carried out across and close to public infrastructure and sensitive elements in the surrounding area, such as the petrochemical industry and a complex network of cables and pipelines. The two trough structures we built can be classified as challenging structures. This was due to their location, the skewed rather than perpendicular crossings, the cables and pipelines in place, and the uniquely restricted space. This called for specialist expertise, including special piled foundations installed beside live transport pipelines in the Botlek area. We therefore opted for cast-in-situ, low-vibration or vibration-free piles, installed by Funderingscombinatie Voorbij-Franki. The lengths and diameters, over 20 metres long and more than 720 mm in diameter, were used at this scale for the first time on this project. The formwork for the troughs had to be balanced, as the walls and floors were cast in a single pour. The span, the slenderness of the structure and the skewed crossing all called for a lot of reinforcement. We are talking about two troughs side by side, around 150 metres long.”

Complexity arose from the location, the skewed rather than perpendicular crossings, the cables and pipelines in place, and the uniquely restricted space.

Moving the steel railway bridges into place

The consortium worked in a confined space in an area that is active day and night. The surrounding businesses had to remain accessible at all times. Rik continues: “The logistics involved in moving two new steel arch bridges into place brought additional challenges. Last year, they were moved to their final locations on Mammoet SPMTs (Self-Propelled Modular Transporters). One bridge was transported across the water, driven over pontoons through the lock to avoid putting strain on it. The other was moved over the Thomassentunnel, right next to the operational VOPAK site, where oil is stored. The bridges are 150 metres and 250 metres long respectively. Each weighs 4,400 tonnes. One bridge is narrow and long, the other short and wide. Getting everything safely into position was quite an undertaking!”

The project was carried out across and close to public infrastructure and sensitive elements in the surrounding area, such as the petrochemical industry and a complex network of cables and pipelines.

For Rik, the personal challenge was having to get a lot of work done in a short time. “That puts a lot of demands on collaboration. As companies, we weren’t new to one another, but as individuals, many of us were. We approached the entire project as a joint venture, with everyone pulling in the same direction. That allows you to achieve a great deal as a team.”     

Have a business enquiry for Mobilis? Get in touch

Who worked on Theemswegtracé

  1. construction consortiumSaVeMentioned in 4D BIM keeps Theemswegtracé ‘on track’
  2. clientHavenbedrijf RotterdamMentioned in 4D BIM keeps Theemswegtracé ‘on track’
  3. grid operatorStedinMentioned in The Netherlands’ most complex underground infrastructure area
  4. contract administratorSGS Roos+BijlMentioned in The Netherlands’ most complex underground infrastructure area
  5. TBI companyMobilisIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectTheemswegtracé
  • SubjectRoad construction
  • CompanyMobilis
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.