Longer-lasting asphalt thanks to glass fibre reinforcement
Text Suzanne van Gaale Beeld S&P Reinforcement Benelux

The longer asphalt lasts, the better, provided this can be achieved sustainably. That is why BAM Infra Nederland is using asphalt reinforcement during major maintenance work on the Zeeburgerbruggen on the A10. Specifically, S&P GLASPHALT® GV120-200, a pre-bituminised glass fibre asphalt reinforcement. A key advantage of this type of reinforcement is how quickly it can be installed.
“To give you an idea of how quickly we install GLASPHALT®: we average 1,000 to 1,500 m2 per hour. We have even laid 45,000 m2 in two full days,” says Ton van Loef, Technical & Commercial Adviser at S&P Reinforcement Benelux. S&P is a world-leading manufacturer of materials for strengthening and repairing concrete and asphalt structures. Glass and carbon fibre asphalt reinforcement is one of its products. It is used worldwide to strengthen asphalt and significantly delay cracking. “It is in particularly high demand in areas at high risk of cracking, such as the western part of the Netherlands. But it also adds value when widening roads and on roads with heavy traffic loads, as well as on bridges.”

Seamless compatibility with LEAB asphalt
S&P works closely with BAM, both on the Groot onderhoud Zeeburgerbruggen A10 project and elsewhere in the Netherlands, including on various N-roads in South Holland. As part of the maintenance work on the Zeeburgerbruggen (A10), Rijkswaterstaat is replacing the road surface with asphalt containing 50% recycled asphalt. This asphalt is also produced and laid using less energy. BAM Infra Nederland is the contractor for this special project. BAM is laying its Low Energy Asphalt Concrete (LEAB), which takes less energy to produce than conventional asphalt. “Our asphalt reinforcement works perfectly with this type of asphalt. It has also been proven to be millable and recyclable, and suitable for use on existing, milled and new asphalt.”

Flexible
The reinforcement is installed in the form of mats, or grids. Ton says one of their advantages is that they are flexible and conform to the asphalt, making it stronger. “S&P’s reinforcement grid is fully impregnated with bitumen, and the grid’s junctions are not fixed. This means the grid can be shaped to the underlying surface during installation and laid directly beneath the asphalt surface course. Because it is flexible, it can also be installed in bends with large to medium radii without much effort. The asphalt layer can be laid immediately once the reinforcement has been installed. This reduces the time for which a road has to be closed.”
Paving train
BAM sees clear added value in using S&P asphalt reinforcement. “The bituminised fibres ensure optimum bonding and interaction with the tack coat,” says Harco Pieterse, Regional Technologist at BAM. “The flexible fibres also bond well to surfaces such as milled asphalt. And last but not least, the application speed gives the paving crew a half-hour head start, and the paving train can’t catch up with them.”
Een zakelijke vraag aan S&P Reinforcement Benelux BV? Get in touch
Who worked on Zeeburgerbruggen
- construction companyBAM Infra NederlandMentioned in Rijkswaterstaat and BAM join forces for sustainable A10 road surfacing
- sweepers and road surface cleaners
Wolfswinkel ReinigingMentioned in Wolfswinkel Reiniging gets the A10 ready for new sustainable asphalt - main contractor
De Klerk WerkendamMentioned in Integrated project safeguards Amsterdam’s flood protection - administratorWaterschap Amstel, Gooi en VechtMentioned in Integrated project safeguards Amsterdam’s flood protection
Keep following this
Get an email when a new story is published. No account needed.
- ProjectZeeburgerbruggen
- ThemeExtending the life of roads and civil engineering structures
- SubjectRoad construction
- CompanyS&P Reinforcement Benelux BV