Water infrastructure

Surfing in the heart of Rotterdam is getting closer: water in the basin!

Image Andre Sprong fotografie

Surfing in the heart of Rotterdam is getting closer: water in the basin!

From 6 May, we will be filling the construction pit for outdoor surf pool RiF010 in Rotterdam with water! No less than 4,500,000 litres of purified canal water will flow into the basin!

RiF010, an outdoor surf pool in the heart of Rotterdam

It all started in 2014, after RiF010 won Rotterdam's last civic initiative competition. RiF010 is being built at the far end of the Steigersgracht, between the Markthal and the Koopgoot. Given the complexity of the project in the city centre, it has taken a while to get off the ground. Mobilis has been involved with RiF010 as adviser and contractor since the initial phase. Hellebrekers

Wave pool

The wave pool is 130 metres long and 21 metres wide, and is being built in an existing canal. Concrete walls have been installed to create a basin in the canal, separating the wave pool from the Steigersgracht itself. The basin slopes from the deep end to the shallow end, eventually ending in a pebble beach. The deep end is by the Grote Markt, and waves are generated from this end. The wave system generates waves up to 1.5 metres high. They travel from this end towards the Wezebrug, where they break on the pebble beach. An artificial reef makes the waves break. At the end of the wave pool, a smaller wave forms that is suitable for beginners.

The beach house

The wooden beach house is being built in the small basin of the Steigersgracht, on the Vlasmarktbrug side. It consists of a basement, two floors and a covered terrace. It will provide changing facilities, catering and a surf shop. The steel structure will be clad in timber. 

Systems

The basin has two systems: one to purify the water and one to generate the waves. Hellebrekers designed and built this system specifically for the project, and it is unique in the world.

The wave system consists of 8 blowers, each capable of generating a 1.5-metre-high wave on average every 7 seconds. Each blower is housed in its own so-called wave chamber. Different presets or settings will allow waves to be generated for every target group. A water treatment system (drum filter) filters the water in the Steigersgracht. 

A partnership

Under this design and build (D&B) contract, Mobilis is responsible for both the design and construction. The partners involved are:

  • Morfis Architecture & Urbanisme (architect)
  • Hellebrekers (systems)
  • D. Bastenhof Consultancy (systems)
  • Surfloch (systems)
  • WSP Ingenieurs (pavilion structure)
  • 2D Vastgoed (development)
  • TBI, engineering, construction and infrastructure group

Have a business enquiry for Mobilis? Get in touch

Who worked on RiF010

  1. constructionMobilisMentioned in Surfing in the heart of Rotterdam, we’re making it happen!
  2. pavilion constructionWSPIn this story
  3. architectMorfis Architecture & UrbanismeIn this story
  4. building servicesHellebrekersIn this story
  5. building servicesD. Bastenhof ConsultancyIn this story
  6. building servicesSurflochIn this story
  7. development2D VastgoedIn this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectRiF010
  • SubjectWater infrastructure
  • CompanyWSP
  • CompanyMorfis Architecture & Urbanisme
  • CompanyHellebrekers
  • CompanyD. Bastenhof Consultancy
  • CompanySurfloch
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.