Robust sealing with bentonite mats at the Westkolk of Born Lock
Text Roel van Gils Image Naue

A challenging follow-on project to the widening of the Julianakanaal
After installing no less than 500,000 m2 of bentonite mats at record pace during the widening of the Julianakanaal, the forebay of the Westkolk at Born lock complex marks the final stage of Naue’s work. Although the project is 20 times smaller than the earlier works, it presents a greater challenge in terms of complexity.
Naue’s involvement in the Julianakanaal began in spring 2024, says Rijk Gerritsen, Technical Director at Naue Nederland. “At the time, we began intensive field trials to test the bentonite mats under the specific conditions of the canal. These conditions are unique: heavy armourstone and even concrete are placed over the sealing layer for protection. All of this places high demands on the robustness of the sealing system. During the field trials, the bentonite mats were subjected to extreme loads, for example by dragging ship’s anchors across the stone revetment and driving cranes over it.”


Robust sealing
Naue’s Bentofix® bentonite mats emerged undamaged from all the field trials. The tests gave a high level of confidence in the material’s robustness and long-term sealing performance. “For high-performance sealing, our mats are made with high-quality bentonite powder. On contact with water, they swell evenly to form a tight seal,” Gerritsen explains. “On projects where we have taken samples ten years after installation, our bentonite mats were still meeting the installation specifications. That says a lot about the system’s service life and robustness. Both Rijkswaterstaat and main contractor Van den Herik Sliedrecht were therefore clear about which type of bentonite mat should be used at the Westkolk of Born Lock.”
Exceptionally complex
During the widening of the Julianakanaal, the lock chamber was used as a temporary silt deposit because all the silt dredged from the canal could not be removed immediately. The silt has since been removed and the entire western forebay has been cleared. The required bed protection is now being installed in this final section too.
According to Gerritsen, the bentonite mats supplied by Naue are among the heaviest in their category, weighing almost 15 kg/m2 and featuring thick protective geotextiles. An integrated sand layer protects the mats during placement of the armourstone layers. Although ‘only’ 30,000 m2 of bentonite mats are being installed at the Westkolk of Born lock complex, the work is considerably more complex. “Unlike the relatively straight earlier canal section, the lock chamber has numerous recesses, mooring piles and sheet piles, and a tightly scheduled programme of works,” says Gerritsen. “The bentonite mats have to be connected to mooring piles and sheet piles in geometries that are extremely challenging. At the same time, several workstreams are constantly overlapping: replacing mooring piles, installing the sealing layer and then placing the heavy armourstone on top of the mats.”

Integrated approach
Naue’s team is responsible for the full package: design, supply and installation, as in the previous phase. “This integrated approach, combined with the trust between the client, contractors, subcontractors and suppliers, makes it possible to deliver complex projects like this quickly and to a high standard,” Gerritsen emphasises. “With all parties working from one site office, communication is direct and decisions are made jointly and quickly. The Association of Water Builders now even uses this approach as a model example of modern collaboration on infrastructure projects. Looking back at what all the project partners achieved during the widening of the Julianakanaal, with a construction period of just nine months, it would have been completely impossible otherwise. We are all incredibly proud of that.”
Naue’s team will install the bentonite mats in the Westkolk from late October to mid-December 2025. The temporary dam will be removed in February 2026, after which the remaining section of the seal can be installed and the water let back in. This will ensure the forebay of the Westkolk is ready for the future.
Question about this story? Ask your question
Who worked on it
Westkolk Sluis Born
- bentonite matsNaue
- clientRijkswaterstaat
- main contractorVan den Herik Sliedrecht
Keep following this
Get an email when a new story is published. No account needed.
- ProjectWestkolk Sluis Born
- SubjectWater infrastructure
- CompanyNaue
- CompanyRijkswaterstaat
- CompanyVan den Herik Sliedrecht