One of the three consortia selected by the municipality of Amsterdam to replace inner-city quay walls is G-Kracht. Gebroeders de Koning, Van Gelder and Giken Europe have joined forces to bring their innovations together. The consortium has now successfully completed the Research and Development Phase, including a pilot project.

The drilling rig in action, installing the small tubular piles as infill between the large tubular piles.

Edwin Boonstoppel, project manager at Gebroeders de Koning, explains: “Through its Bridges and Quay Walls programme, the municipality of Amsterdam is aiming to accelerate the work significantly compared with the preceding decades, when quay walls were replaced only at a very limited rate. The tendering procedure began in 2018. From 2020 onwards, as one of the selected parties, we developed our innovative idea into a design ready for construction, which we then demonstrated in a pilot project on the Singel.”

The three G-Kracht partners worked on the pilot project with a number of suppliers and subcontractors, within the framework set by the municipality. These included ArcelorMittal, which supplied the steel tubular piles; De Vries-Titan, which installed the grout anchors; the Rutte Groep, which carried out demolition work on the top section of the existing quay, provided electric transport by water and manufactured concrete elements with brickwork; and Lommers Welding, which carried out the welding.

Over the next eight years, G-Kracht will deliver at least 3,300 metres of quay, including the 204 metres completed during the pilot.   

The final tubular pile is being drilled into place as onlookers watch.

Technical expertise

Edwin: “As a contractor, Gebroeders de Koning builds quay walls, bridges, tunnels and viaducts at the boundary between land and water. To explain the division of responsibilities within G-Kracht: we build the quay wall itself, while Van Gelder carries out all the work around it.”

Mark Geertman, environmental manager at Aannemingsmaatschappij Van Gelder, explains: “We specialise in both above-ground and underground infrastructure, covering road surfacing, sewerage, cables and pipelines. We have extensive experience of long-term maintenance for the municipality of Amsterdam. Our environmental management is one of the ways we distinguish ourselves.”

Job Vaessen, business development manager at Giken Europe BV: “We specialise in pressing steel tubular piles and sheet piles into the ground. We also developed what is known as gyro technology, which rotates tubular piles as they are pressed into the ground. A toothed ring bit is welded to the bottom of the tubes, allowing them to drill through existing obstacles. No soil is displaced in the process, it remains inside the tube. Gebroeders de Koning has been one of our customers for a long time. They asked us how we could help with this project.”

Giken Europe hires out the machinery and provides the technical expertise. The company developed a scaled-down version of its GRB system specifically for Amsterdam. The system was already used for large-scale applications elsewhere in the world. The innovation lies in reducing the size of the equipment as much as possible so it can be used in a dense urban setting with limited working and construction space. Specifically, the system comprises three pieces of equipment, all electric: a gyropiler, a clampcrane and a pilerunner. Giken also developed and patented the ring bit.

G-Kracht’s worksite, with the gyropress and clampcrane operating beneath one of the tree canopies.

Challenge

G-Kracht was tasked with renewing quay walls in half the time, at half the cost and with half the disruption of traditional methods. This was a challenge, as it effectively required an eightfold improvement on the traditional construction method. The pilot has now demonstrated that G-Kracht can successfully achieve all three. This represents radical innovation.

The reduced disruption is already evident from the fact that both the road and the waterway remain open. Boats can pass the work zones, and the road along the quay stays open to cars, cyclists and pedestrians.

The process starts by filling the cavities beneath the floor of the existing quay wall. Over the years, the propellers of tour boats have washed sand out from beneath the wall, creating cavities in many places. Filling these cavities prevents future subsidence.

The top section of the quay wall is removed, down to just above the waterline. The coping stones are reused and will be put back later. Giken’s Gyropress then comes into play, rotating and pressing steel tubular piles into the ground. The 500 mm diameter tubes are installed at 750 mm centres, leaving a 250 mm gap between them. A clampcrane feeds the tubes to the Gyropress. Both pieces of equipment travel over the piles already installed, so neither is in the water. The system is highly flexible and can be used regardless of the shape of the quay. The tubular piles are 14 or 22 metres long and are installed in a pattern of two long piles reaching the second sand layer and four short piles reaching the first. Once the piles are in place, the walls are stable under unloaded conditions, meaning without traffic.

The structural wall is complete. It is clearly visible that it has been drilled through the existing quay wall, with the rear section left in place and the front section removed.

Innovating throughout the process

The next step is to install short, small piles in the gaps on the landward side. The pressure of the soil pushes these small tubular piles against the large ones, creating a complete seal. Holes are drilled in one in every five piles, and a filter system is then installed inside the tube to keep the groundwater level at the same height as the water in the canal. This makes the wall soil-tight but permeable to water.

During the pilot, Lommers Welding then began installing the anchor waling. This is welded on site as a horizontal H-section, which accommodates the heads of the tubular piles. In this way, the waling follows the alignment of the quay, both horizontally and vertically. The anchors installed behind the structure are connected to it. De Vries-Titan drilled these into the ground at a steep angle, with the anchors remaining in front of the buildings’ façades. This is a requirement set by the client.

A good example of continuous innovation throughout the process: for low quays, anchors will almost certainly no longer be needed in the future.

The final section of the old quay wall is then removed. Within two days, the Rutte Groep completed the entire frontage of the new quay using precast elements with the brickwork already in place. Only the joints between the elements were bricked up on site. Van Gelder then reinstated the reused coping stones and repaired the paving, after which the parking spaces were reopened to traffic.

Mark: “Local residents compliment us on how little noise and vibration our work causes. And the trees along the canals remain in place throughout the process, which is a form of climate-adaptive construction.”

Job adds: “All the equipment has been developed to produce no emissions. The Netherlands is extremely far ahead in electrification, by as much as ten to fifteen years compared with other countries. If there is enough power available on site, we can renew our quays with no emissions.” If it can be done in Amsterdam, it can be done anywhere.  

Een zakelijke vraag aan ArcelorMittal Projects Europe B.V.? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectWater infrastructure
  • CompanyDe Vries Titan B.V.
  • CompanyArcelorMittal Projects Europe B.V.
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.