Four construction seasons to build the most sustainable dike in the Netherlands

Text Roel van Gils Image Combinatie Waddenkwartier

De werkzaamheden verlopen tot op heden keurig volgens planning.
De werkzaamheden verlopen tot op heden keurig volgens planning.

In the north of the Netherlands, Combinatie Waddenkwartier is working to strengthen the Groningse Lauwersmeerdijk. The consortium, comprising Heijmans and GMB, was awarded the project in 2020 under a two-phase contract by client waterschap Noorderzijlvest. Construction on site began in April 2023 and will take a total of four ‘construction seasons’. Project manager Gérard Porton takes us along the dike and discusses the steps involved in creating the most sustainable dike in the Netherlands.

The project is due to run until 2027, after which the Groningse Lauwersmeerdijk will once again meet safety requirements for at least 50 years.

The Groningse Lauwersmeerdijk runs between Lauwersoog and the Westpolder. The dike no longer meets safety requirements and therefore needs to be strengthened. “Based on the preliminary design drawn up by the water board and assessed for buildability, opportunities and sustainability, we, as the construction consortium, prepared the detailed design and construction design,” says Gérard. “We were awarded the construction contract on 17 February 2023 and began work on site. The work will take four years, or more accurately, four construction seasons running from April to October. During the storm season, we are not allowed to carry out any work on the seaward side. We can, however, complete work on the landward side, which gives us a little more time.”

The old dike revetment is being removed and replaced in full with a stronger, heavier version.

Linked projects

As well as strengthening the dike along a length of 9.2 kilometres, a number of linked projects are also being carried out. “These are projects that directly interface with the dike and which the water board has added to the dike reinforcement in collaboration with Het Hogeland municipality, the province of Groningen, Rijkswaterstaat, Groninger Landschap on behalf of the cooperating nature organisations, and Defensie,” Gérard explains. “This allows projects to make smart use of the work being carried out on the dike. If you miss an opportunity like this, it may be a long time before you get another chance. Seven linked projects were identified in advance, and all seven are being delivered as part of the works. They range from renovating the Westelijke Havendam and building a second access road to the harbour to constructing a cycle path over the dike, modifying Defensie’s maintenance road, and three ecological projects to boost biodiversity on and around the dike and in the Wadden Sea.”

As well as strengthening the dike along a length of 9.2 kilometres, a number of linked projects are also being carried out.

Demonstrably sustainable

The ambitions of the consortium and the water board are considerable. “We have agreed to create the most sustainable dike in the Netherlands. Of course, that is a snapshot in time, as development continues unabated. In any case, 100% of all materials arising from the works will be reused, from the asphalt and copper slag blocks to the clay and concrete products,” says Gérard. “By reusing all the clay, we need to import far less class 1 clay, which makes a huge difference to the number of transport movements and therefore to CO2 emissions. We also source almost all construction materials from within a 50-kilometre radius of the site. Only the armourstone comes from further afield. In addition, we are using as much electric plant as possible, reducing greenhouse gas emissions on site during construction by around 50%. Heijmans and GMB are not doing this alone. We have persuaded several companies in the region to invest in electric plant as well.” Combinatie Waddenkwartier can also demonstrate the impact of these sustainability measures. “When developing the project plan, we produced a sustainability report that also substantiates our ambitions and measures.”

The dike is being raised by between 70 and 100 centimetres along its entire length, depending on the location.

Three sections

Back to the dike reinforcement itself. “We started work on the border with Friesland, carrying out maintenance on the seaward side at the R.J. Cleveringsluizen, the Lauwersmeer sluices,” Gérard continues. “The old dike revetment is being removed and replaced in full with a stronger, heavier version. We then head towards the harbour at Lauwersoog. The provincial road here was reconstructed a few years ago and runs along the top of the primary flood defence. The reinforcement work here is therefore being carried out outside the provincial road, with a sheet-pile wall and a retaining wall behind it. This approach also creates a promenade with views of the harbour and separates pedestrians from cyclists. The third section is the rural dike, where the revetment is also being removed, the dike raised by up to 100 cm, and then finished in a fairly traditional way with Verkalit stone pitching, asphalt and greenery.”
Work has so far been progressing smoothly and according to plan. The dike is being raised by between 70 and 100 centimetres along its entire length, depending on the location. The project is due to run until 2027, after which the Groningse Lauwersmeerdijk will once again meet safety requirements for at least 50 years.

A business enquiry for GMB? Get in touch

Who worked on it

Lauwersmeerdijk in Groningen in Het Hogeland

  1. clientwaterschap Noorderzijlvest

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectLauwersmeerdijk in Groningen
  • SubjectWater infrastructure
  • Companywaterschap Noorderzijlvest
  • CompanyGMB
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.