Dutch expertise sought for quay wall repairs in the Port of Antwerp

Text Roel van Gils Image Van der Jagt Groep

Ook op dit project bewijst Van der Jagt Groep zijn toegevoegde waarde.
Ook op dit project bewijst Van der Jagt Groep zijn toegevoegde waarde.

Work is under way in the Port of Antwerp to repair and renew a total of 6.5 kilometres of quay wall. Over a stretch of more than 2.2 kilometres, the concrete at the top of the quay wall is in such poor condition that it must be demolished completely. In some places, this means sawing through the top below the waterline. This is where Van der Jagt Groep’s expertise comes in. When a project is large, complex or specialised, clients in the Netherlands and Belgium know they can turn to Van der Jagt Groep.

The work involves renewing more than 2.2 kilometres of quay wall in total, divided into 75 sections, each 30 metres long.

Van der Jagt Groep excels at coming up with creative solutions for challenging demolition and renovation projects. “The project in the Port of Antwerp is a great example,” says Machiel Wijland of Van der Jagt Groep. “Artes Group, the Belgian contractor on the project, was a new client for us. But after a few discussions, they were pleasantly surprised to find that we could take on all the work ourselves. In Belgium, they are more used to having one subcontractor for the sawing, another for the demolition, and so on. On this project, we are handling everything, from sawing through the quay wall and demolishing it to drilling and bonding starter bars for the new quay wall coping.”

Van der Jagt Groep started work on the large-scale project in October 2023.

75 sections

Van der Jagt Groep started work on the large-scale project in October 2023. “The work involves renewing more than 2.2 kilometres of quay wall in total, divided into 75 sections, each 30 metres long,” explains Machiel. “Depending on the condition of the wall, we demolish around 2 to 3.5 metres of concrete from the top. First, we make a horizontal saw cut at the break-off level, then use a demolition excavator with a hydraulic breaker to remove the upper section of the wall. We collect the rubble, store it temporarily on the quay and then remove it from site. Once the sawing and demolition are complete, we drill 80 holes, 50 mm in diameter and around 2 metres deep, into the quay wall. We bond the starter bars into these holes. The steel fixer then ties the reinforcement cage, and finally we cast a new quay wall coping.”

Van der Jagt Groep works to a one-week cycle (five working days) for each section.

Underwater sawing and drilling

Van der Jagt Groep works to a one-week cycle (five working days) for each section. “We have been working on the project for almost a year and a half now, and everything is still progressing smoothly,” says Machiel. “The main challenge is the sections that have to be completed underwater. The water level is at 3 metres, while we need to make the saw cut at 3.5 metres. An electric saw cannot do this, so in these locations we use a hydraulic saw. We have also developed a special frame for it. The same applies to drilling the starter bars. We would normally use a drill rig mounted on the excavator with a pneumatic drill motor, but in this case we use the hydraulic circuit of the mobile excavator. This brings several disciplines together, as we also blow air and water through the drill rod to flush out the hole. Otherwise, we would never reach a depth of 2 metres. 

This project is another demonstration of Van der Jagt Groep’s added value. When a project is large, complex or specialised, clients in the Netherlands and Belgium know they can turn to us. “We expect to demolish and repair the final sections on schedule in January 2025.”      

A business enquiry for Van der Jagt Groep? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectWater infrastructure
  • CompanyVan der Jagt Groep
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.