Water infrastructure

Delivering quality just above the waterline

Text Tony VosImage Lommers Welding Services

Welding from the water's edge.
Welding from the water's edge.

As part of the G-Kracht project, the pipes installed behind the original quay wall are connected at the top by a welded structure. Lommers Welding Services, based in Purmerend, was brought in as the welding contractor for this specialist work.

Lommers Welding works to standards including VCA, NEN 1090, ISO 3834-2 and ISO 9001. “An important requirement for this project was that we work with full certification and carry out our work in accordance with the prescribed standards,” says Gerda Lommers.

The company was involved in the project at an early stage. “We contributed ideas on the innovation expected by our client and the municipality of Amsterdam. Our materials and equipment are transported to Amsterdam-Noord using electric vehicles. From there, everything goes by boat to the work site.”

Lommers Welding installs the walers around the piles.

A unique approach

Lommers Welding is a family business with an established reputation in the welding industry. It carries out large-scale projects on site and in its own workshop, delivering a complete package from design through to execution.

Gerda: “For the G-Kracht project, we install the walers around the piles. We weld a plate between the piles and a flange on both the front and back. This makes the structure much stiffer. After our work, it forms a single unit. Anchors are then installed at regular intervals to stabilise the entire quay structure and keep the carriageway in place.”

The G-Kracht approach differs from standard practice. “We have never used this type of structure before, where a beam is integrated with the pipes. The use of anchors at a 70-degree angle is also specific to this project.”

For the stiffening structure, Lommers Welding prefabricated as much as possible to reduce the time needed on site. This also helped minimise disruption to the surrounding area. Lommers also installed the supports for the so-called aprons, the prefabricated quay walls. All materials and welding methods used comply with CE standards.

Wet conditions

Water and welding are generally considered incompatible. Lommers Welding works just above the waterline in wet conditions from a pontoon. All the welding for the pilot project on the Singel has now been completed to execution class 2, in accordance with NEN-EN 1090.

Gerda: “It has turned into a wonderful project. I’m really proud of what we have achieved together. We met the schedule and quality requirements in full. A great bonus is that both the municipality and local residents are very satisfied. The project was an enjoyable challenge for our employees. We are pleased that everyone involved is positive about it.” 

Question about this story? Ask your question

Who worked on it

G-Kracht in Amsterdam

  1. welding companyLommers Welding Services

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectG-Kracht
  • SubjectWater infrastructure
  • CompanyLommers Welding Services
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.