Water infrastructure

Cost-effective sewer diversion and upsizing

GW Leidingtechniek is een bekende naam bij vele waterschappen, drinkwaterbedrijven en infra-aannemers in ons land.
GW Leidingtechniek is een bekende naam bij vele waterschappen, drinkwaterbedrijven en infra-aannemers in ons land.

The route of the new N69 crosses two existing wastewater pipelines belonging to Waterschap De Dommel, dating from the 1970s.

Part of Boskalis’s contract was to divert and upgrade a section of the pipelines. During the tender, GW Leidingtechniek devised a cost-effective alternative to the initial requirements.

GW Leidingtechniek is a familiar name to many water authorities, drinking water companies and infrastructure contractors in the Netherlands. “We specialise in pipeline engineering, particularly for wastewater and sewage,” says Rense de Keijser, project manager at GW Leidingtechniek. “We carry out our work almost always as the main contractor, and in recent years increasingly as part of a construction team. In this particular case, we were a subcontractor. In addition to construction, we are also very strong in consultancy and (3D) design. That is why Boskalis involved us from the tender stage for the design and construction of two existing pipeline routes on the new N69.”

GW Leidingtechniek always works thoroughly and leaves nothing to chance.

Substantial savings

Construction of the new N69 affected the existing sewer network of Waterschap De Dommel at two locations. “At Riethoven, at the Takkers junction, we had to replace around 80 metres of the existing route with a sustainable alternative. At the junction with the N397 near Westerhoven, the existing route had to be diverted,” explains De Keijser. “Under the water authority’s initial requirements, temporary pumping installations would have had to operate for seven weeks to allow the work to be carried out. We devised an alternative: first, we prefabricated as much of the new pipelines as possible and pressure-tested them, then switched over to the new routes in a single 12-hour working day. This meant the old pipeline remained in service for as long as possible. We were able to cut costs considerably and reduce the environmental impact. The temporary pumping installations only had to be hired and operated for a limited number of days, rather than for many weeks.”

Construction of the new N69 affected the existing sewer network of Waterschap De Dommel at two locations.

Prefabrication

At the Takkers junction near Riethoven, GW Leidingtechniek replaced the existing PVC pipeline with a new PVC gravity sewer pipe in a protective casing. De Keijser says: “The old sewer pipeline had become deformed, more oval than round.   

“We first prefabricated the entire new route, comprising 80 metres of 315-millimetre-diameter PVC pipe, 60 metres of which was inside a GVK casing with a diameter of around 530 millimetres. The whole assembly, including the manhole, was put together on site, tested and pressure-tested. Then, in a single day, we took the existing system out of service, cut through it, pumped it empty and connected the new route. The sewer was back in operation within eight hours.” 

The old sewer pipeline had become deformed, more oval than round.

Ingenuity

The work at the bottleneck near Westerhoven was somewhat more complex. De Keijser says: “Here we installed a 1,200-millimetre GVK pipeline along a new route, including four manholes and several ditch crossings. We then installed a temporary pumping system so we could connect the new route, around 350 metres long, to the existing system at both ends. After that, we removed the old concrete pipes. Connecting the new route to the existing, 70-year-old network calls for considerable ingenuity, particularly as materials of this kind are no longer available new. That is where our strength lies, backed by a huge store of in-house knowledge and expertise. We always work thoroughly and leave nothing to chance. This commitment and solutions-focused approach are embedded throughout our company, not just among the project managers but also with our teams out in the field.” 

As well as carrying out the work, GW Leidingtechniek is also highly skilled in consultancy and (3D) design.

Fully self-sufficient

Conditions in the field on the N69 were very wet. “Groundwater levels were very high during the period when we carried out the work in 2020,” recalls De Keijser. “We also had to provide dewatering. There were as many as ten pumps running along a stretch of just 100 metres.” GW Leidingtechniek is fully self-sufficient. “We have our own dewatering pumps, road plates, dragline mats, lighting towers and HDPE welders with welding equipment. We are also certified, among other things, to install GRE pipes, that is, fire-retardant GVK pipes, and fire mains. In recent years, we have also become increasingly active in sewer network rehabilitation, for which we have developed specific solutions, such as a rehabilitation method that avoids having to excavate the entire network. At intervals, we create access points from which we can insert GVK liners into the existing system with very little disruption. The liners are grouted around the circumference, restoring the network for at least another 50 years.”

GW Leidingtechniek prefabricated and pressure-tested as much of the new pipelines as possible, then switched over to the new routes in a single 12-hour working day.

“Coming up with innovative techniques or alternative methods is in our DNA,” concludes De Keijser. “We proved that on the N69 too. Since infrastructure contractors, water authorities and drinking water companies are all among our clients, we always communicate directly with the stakeholders. In this case, Boskalis did not have to act as an ‘intermediary’. That allows us to skip several steps in the design process, which works very well. We were able to take full responsibility for our scope on the N69 and relieve Boskalis of the associated work.”     

Een zakelijke vraag aan GW Leidingtechniek BV? Get in touch

Who worked on N69

  1. senior site managerBoskalisMentioned in Broad support as the foundation of Brabant’s greenest road
  2. clientProvince of North BrabantMentioned in Broad support as the foundation of Brabant’s greenest road
  3. traffic management measuresBUKO InfrasupportMentioned in Traffic flow and safety key to construction of Grenscorridor N69
  4. design of the structuresNobleoMentioned in Interdisciplinary design
  5. road designGeoniusMentioned in Interdisciplinary design
  6. Vehicle barrierVan Straten Geleiderail B.V.Mentioned in 100% circular vehicle restraint system
  7. lighting designDynniqMentioned in No lighting unless safety is at risk
  8. structural designNobleo Bouw & InfraMentioned in Design and spatial quality make the difference
  9. supplied formwork ribsMZ BekistingenMentioned in Valuable formwork advice
  10. subcontractorGW LeidingtechniekIn this story
  11. reinforced earth structuresVoets Gewapende GrondconstructiesMentioned in Temporary and permanent reinforced soil structures
  12. regular supplierHueskerMentioned in Temporary and permanent reinforced soil structures
  13. mixing plantGebroeders Van den Brand en Van OortMentioned in 40,000 tonnes of bound asphalt granulate (AGRAC)
  14. transportA. van Grunsven TransportMentioned in 40,000 tonnes of bound asphalt granulate (AGRAC)
  15. architectNEXTMentioned in Brabant’s greenest link
  16. landscape architectsH+N+S LandschapsarchitectenMentioned in Brabant’s greenest link
  17. transport company and soil bankVan Grunsven en Langenhuijzen TransportMentioned in Guaranteed supplies of earthworks materials
  18. soil bankSlibbank NederlandMentioned in Guaranteed supplies of earthworks materials

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectN69
  • SubjectWater infrastructure
  • CompanyGW Leidingtechniek BV
  • CompanyBoskalis Nederland