Guaranteed supplies of earthworks materials

A huge volume of earthworks and construction materials was delivered for the construction of the new N69.
To take care of all these requirements for main contractor Boskalis, Van Grunsven en Langenhuijzen Transport and Slibbank Nederland joined forces as partners to get the job done together. A collaboration that has left all parties wanting more.
“Contractors increasingly want to be relieved of the burden and know upfront what they will be ‘in for’, especially on large projects such as the N69,” says Anton van Grunsven, director of Van Grunsven en Langenhuijzen Transport. “Bringing in a random soil bank and transport company often makes things no easier for the main contractor. It also requires a fair amount of coordination. We stepped into that gap by putting together a joint proposal as a transport company and soil bank. This included all the ancillary work, installing weighbridges and coordination. So we take care of everything that comes our way and remove risks for the main contractor.”

Regional supply
Between November 2019 and April 2021, the partnership delivered more than 700,000 tonnes of sand and soil, as well as a further 100,000 tonnes of construction materials. “The aim was to source as much of the delivered soil as possible from the region, making the most of work already under way,” says Bjorn Vissers of Slibbank Nederland. “That is Slibbank Nederland’s area of expertise. We received offers from more than 1,000 different parties to supply sand and soil. We were able to use just under 500 of them on this project, as at the time of planning they met the project’s needs and the civil engineering requirements. Most of the materials did indeed come from regional projects across Brabant, and only on a few occasions did we go beyond the province. This enabled us to serve construction projects and soil banks in the region effectively as a regular outlet.”

A complex puzzle
Naturally, all supplies meet statutory requirements. Vissers explains: “When a batch of soil is offered, its quality is assessed both for civil engineering purposes and on environmental grounds. We prepare a report and, once it has been approved, arrange the contract and complete all the necessary paperwork in accordance with the Soil Quality Decree. The logistics for deliveries to the N69 were then scheduled through the planning team at Van Grunsven en Langenhuijzen Transport. We had a coordinator on site to manage both the soil flows and the lorries. Boskalis wanted the soil to be placed directly in the correct location.” Van Grunsven adds: “The coordinator was also the first point of contact for the Boskalis site manager. Every day was different.
Deliveries were closely tied both to Boskalis’ schedule and to what was available on the market. It was sometimes a complex puzzle, made more challenging by the need to stick to fixed routes to limit the impact on surrounding villages.”

Complete and accurate records
Given that a tipper truck can carry an average of 30 tonnes of sand, there were quite a lot of vehicle movements. “At least 30,000,” Van Grunsven estimates. “As well as our joint contract with Slibbank, we also had a contract to deliver hot asphalt and remove planings. We tried to combine as many loads as possible to maximise the utilisation of our vehicles. In effect, all soil was either delivered to or removed from the site by us. Boskalis delivered the soil for the earthworks itself. To keep everything running smoothly and maintain an overview, weighbridges were installed at both ends of the site. Everything entering the site was weighed, resulting in complete and accurate records.”

The project has now been completed for Slibbank. The bulk of the work is also behind Van Grunsven en Langenhuijzen Transport. “That said, we will still be delivering a fair amount of hot asphalt in the coming period. When the site cabin compounds are dismantled, we will also help leave the landscape in good order.” Both men look back on a smooth and enjoyable collaboration. “As two specialist companies, we complement each other on infrastructure projects of this kind. We can take care of everything for infrastructure contractors. Boskalis placed its trust in us, and we delivered. The collaboration has left us wanting more.”
Have a business enquiry for Boskalis Nederland? Get in touch
Who worked on N69
- clientProvince of North BrabantMentioned in Broad support as the foundation of Brabant’s greenest road
- traffic management measures
BUKO InfrasupportMentioned in Traffic flow and safety key to construction of Grenscorridor N69 - reinforced earth structures
Voets Gewapende GrondconstructiesMentioned in Temporary and permanent reinforced soil structures - mixing plantGebroeders Van den Brand en Van OortMentioned in 40,000 tonnes of bound asphalt granulate (AGRAC)
- transport company and soil bankVan Grunsven and Langenhuijzen TransportIn this story
- soil bankSlibbank NederlandIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectN69
- SubjectNews
- CompanyVan Grunsven and Langenhuijzen Transport
- CompanySlibbank Nederland
- CompanyBoskalis Nederland