Temporary and permanent reinforced soil structures

The structures on the new N69 include two permanent and six temporary reinforced soil structures.
Voets Gewapende Grondconstructies was involved by Boskalis at the pre-construction stage. “Integrating reinforced soil structures into the design not only improves a project’s sustainability, but ultimately also makes it more cost-effective,” says managing director Gino Jongmans.
Voets specialises in the detailed design of reinforced soil structures, as well as their supply and installation. “Boskalis is a long-standing client and has trusted our expertise for many years,” says Jongmans. “They often see us as a strategic partner and bring us in at an early stage. Although our contribution to the N69 is relatively small, our structures have nevertheless become part of the integrated design.” Constant Brok, design manager at Voets for the N69, adds: “At structures 09 and 13, reinforced soil has been used as a permanent structure, partly as a foundation and partly as walls. At six other locations, we built temporary reinforced soil structures to serve as temporary works.”
Locally sourced material
According to Jongmans, building with reinforced soil is a considerably more sustainable and economical alternative to using steel sheet piles or concrete structures. “We make as much use as possible of the principle of making use of the work already being done. Excavated soil from elsewhere on the project is often used as fill for the reinforced soil, for example to raise an abutment. That was also done here on the N69. The great thing about our work is that we never build structures in isolation. We always work closely with the main contractor, because they manage the earthworks balance. Another advantage of reinforced soil structures is that they can be built quickly. We can build much faster than with traditional steel or concrete methods.” Brok says: “As well as constructing the foundations for both structures, we are also building the wing walls, the retaining walls beside the bridge, using reinforced soil, sand and geogrids. Instead of a 1:1 slope, we can build at 90 degrees using locally sourced soil, which is then finished with a thin concrete facing.”
Complete reinforced soil solutions
The temporary reinforced soil structures on the N69 are primarily intended to create space for constructing the decks of the structures. “The abutments are founded at a relatively shallow depth. We needed mass to provide resistance and support the future deck during construction,” explains Brok. “We achieved this with a reinforced soil structure that will later be reconfigured to take its permanent form.” Jongmans says: “We offer complete reinforced soil solutions and contribute to the integrated design process to arrive at the most efficient design. We work with Huesker as our regular supplier of the required soil reinforcement. As well as being a reliable partner, it is a major global player in geotextiles. The N69 project is now nearing completion for us. We look back on a great project, working comfortably with the main contractor in a safe and healthy environment.”
Een zakelijke vraag aan Voets Gewapende Grondconstructies B.V.? Get in touch
Who worked on N69
- clientProvince of North BrabantMentioned in Broad support as the foundation of Brabant’s greenest road
- traffic management measures
BUKO InfrasupportMentioned in Traffic flow and safety key to construction of Grenscorridor N69 - regular supplierHueskerIn this story
- mixing plantGebroeders Van den Brand en Van OortMentioned in 40,000 tonnes of bound asphalt granulate (AGRAC)
- transport company and soil bankVan Grunsven and Langenhuijzen TransportMentioned in Guaranteed supplies of earthworks materials
Keep following this
Get an email when a new story is published. No account needed.
- ProjectN69
- SubjectNews
- CompanyVoets Gewapende Grondconstructies B.V.
- CompanyHuesker
- CompanyBoskalis Nederland