Complex tubular piles

Herstaco demonstrated its full added value during construction of the Nieuwe Sluis in Terneuzen. One of Europe’s largest stockholding suppliers of steel tubes can also process and assemble them to customer specifications at its own site in Middelburg. Contractor consortium Sassevaart made grateful use of this capability.
“We supplied 61 tubular piles in phases, with a diameter of 1,420 mm and varying lengths from 37 to 43 metres,” begins Bas Verschoore, Sales Manager at Herstaco. “A steel tube has a standard commercial length of 11-12 metres, so we welded different stock lengths, also with varying wall thicknesses, together to achieve the required lengths and resistance to pressure. Within the tolerances, we looked for as many ways as possible to optimise the lengths. On the one hand, to minimise waste, and on the other, to keep the total weight as low as possible for the application. After all, payment is by the tonne.”
In a class of its own
Because the tubular piles were installed using a fairly innovative method, Herstaco not only welded circumferential joints and fitted interlocks for sheet piles, but also welded caps into the tubular piles. Verschoore: “The piles were filled with water so that their own weight would make them sink slowly into the bentonite mix. We therefore first welded the caps into the stock lengths before we could weld the circumferential joints. It was quite a puzzle, especially as each pile combined different wall thicknesses. This also meant that we had to taper some pile sections to make the weld. All the steel we supplied was, of course, certified and fully traceable. All in all, this was an exceptional order for us, given the amount of processing involved, but it went very smoothly. We’d be happy to do more,” concludes Verschoore.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectWater infrastructure