A massive structure with minimal tolerances
Text Suzanne van GaaleImage DYWIDAG

Millimetre-precision work at height
One of the salt dam’s key components is its piers, which are 27.5 metres high, 8 metres wide and weigh almost 3,000 tonnes. The pier construction is also the most important part of the project for DYWIDAG, which is responsible for the stressing system. It is literally millimetre-precision work at height.
“The biggest challenge in this project is that it involves immense forces, a huge structure and minuscule tolerances,” says Robert Jansen, business unit manager at DYWIDAG. “The piers are precast on site, lifted to their final location and then positioned. Our work focuses above all on the lifting point. The principle is that this point must not separate from the concrete structure beneath it during lifting. This means the lifting point must be pressed against the structure beforehand. To withstand these forces, we designed a massive structure that uses high-strength bars to clamp the lifting point to the concrete structure. Without this, the point would separate from the concrete, which is something you want to avoid. This is why we introduce the forces into the structure in advance. That is our speciality.”

Precision work
This prestressing is carried out using bars made from high-grade steel (prestressing steel). The prestressing force pressing the lifting point against the structure must be greater than the tensile force generated when the pier is lifted. DYWIDAG was brought in once a basic design was already in place. “However, it was so large that it would not fit within the configuration. Together with the Van Hattum en Blankevoort team, we started looking for alternatives. What would fit? After a great deal of calculation and fine-tuning, and producing the necessary mock-ups, we settled on a total of 44 bars, each 57 millimetres in diameter, per pier, 11 at each corner. We often do highly customised work, but never on this scale. Our bars normally go up to 40 millimetres in diameter, but here we are using 57-millimetre bars. It is a step up in size and weight, while the dimensions need to be more precise. A single lifting frame will be placed over them, with 22 bars needing to be in exactly the right position at the same time.”
One centimetre of clearance
The bars are anchored in the concrete. To provide sufficient ‘body’, they are built in over a length of around 10 metres. “That means they run through several concrete pours, so they have to be connected. Once we reach the highest point of the structure, the lifting point is placed over them. This has to be accurate to the millimetre. At the top, more than 27.5 metres above ground, we have just 1 centimetre of clearance. That makes the dimensions and fit even more complex. You can imagine that it takes considerable coordination between everyone involved to build it together in those conditions.”