Use of pumice in reinforced soil construction for rail is unique in the Netherlands

The old Botlek Bridge has been demolished and the new one built. Cars, cyclists and pedestrians have been using it for some time, but the railway still had to be connected to the port railway network. The work had to take account of the Botlek tunnels beneath it, which carry rail and road traffic, as well as vulnerable industrial pipelines. An additional challenge was the unstable ground.
This prompted Arcadis to ask Geologics, a partner of Joosten Concepts, to design the connection. The solution is unique in railway construction: pumice was chosen as the material for building a reinforced soil structure. This extremely lightweight yet highly stable foundation material, with excellent water permeability, was used on both the western and eastern sides.
Looking to the future
Two sheet-pile walls were installed on the eastern side of the future track, and one on the western side, with a slope on the other side. Formwork that moved up as each layer was built prevented direct pressure on the sheet-pile walls if the structure settled slightly. The void was filled with uncompacted pumice to deter pests and vegetation and allow the structure to bulge out. The key advantage is that this construction method means the sheet-pile walls can be removed and the surrounding area excavated as the area is redeveloped, without affecting the subgrade structure.
Optimum protection
The pumice layers are reinforced with RE Geogrids from Tensar. A Tensar SS20 Geogrid was also installed for mechanical stabilisation, in an optimised 90-centimetre-thick design. Pumice is stronger than sand, but can crush under high pressure. A load-spreading upper layer of sand is designed to prevent this. The sand layer is separated from the pumice by HDPE film to prevent damage caused by moisture ingress or contamination. Beneath the film is a TenCate Polyfelt TS non-woven geotextile for protection. An RE-grid placed directly on the film prevents the sand from slipping. The same RE-grid is also incorporated into the next two to three sand layers as reinforcement.
The project was carried out by Joosten Concepts partners Molhoek-CCT and Loonbedrijf Van Etten. Materials were supplied by Joosten Kunststoffen in collaboration with TenCate and Tensar.
A business enquiry for Joosten Groep? Get in touch
Who worked on Botlekbrug
- Polyfelt TS non-woven geotextileTenCateIn this story
- carried out by
MolhoekMentioned in Pumice used in reinforced soil structure for railway is unique in the Netherlands - carried out byLoonbedrijf Van EttenMentioned in Pumice used in reinforced soil structure for railway is unique in the Netherlands
- materialsJoosten KunststoffenMentioned in Pumice used in reinforced soil structure for railway is unique in the Netherlands
- designGeologicsMentioned in Pumice used in reinforced soil structure for railway is unique in the Netherlands
- contract partner
Croonwolter&drosMentioned in Croonwolter&dros and Elinex deliver Botlek Tunnel emergency power system through to 2035
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBotlekbrug
- SubjectSpecials
- CompanyJoosten Groep
- CompanyTensar International BV
- CompanyTenCate
- CompanyMolhoek Infratechniek