Pumice used in reinforced soil structure for railway is unique in the Netherlands

The old Botlek Bridge has been demolished and the new one built. Road traffic, cyclists and pedestrians have been using it for some time, but the railway still had to be connected to the port railway network. The work had to take account of the Botlek tunnels beneath it, for rail and road traffic, as well as vulnerable industrial pipelines. An added challenge was the unstable ground.
This prompted Arcadis to ask Joosten Concepts partner Geologics to design the connection. The solution is unique in railway construction: pumice was selected for use in building a reinforced soil structure. This extremely lightweight yet highly stable foundation material, which offers excellent water permeability, was used on both the west and east sides.
Looking to the future
Two sheet-pile walls were installed on the east side of the future railway, and one on the west side; the other side is a slope. Formwork that moved along as the layers were built prevented direct pressure on the sheet-pile walls in the event of slight settlement of the structure. The void was filled with uncompacted pumice to deter vermin and vegetation, and to allow the structure to bulge out. The key advantage is that this construction method makes it possible to remove the sheet-pile walls and excavate the surrounding area if new developments take place in the area, without affecting the track formation structure.
Optimum protection
The pumice layers are reinforced with Tensar RE Geogrids. A Tensar SS20 Geogrid was also installed for mechanical stabilisation, in an optimised 90-centimetre-thick design. Pumice is stronger than sand, but can crush under high pressure. An upper sand layer distributes the load and prevents this. The sand layer is separated from the pumice by HDPE film to prevent damage caused by moisture or contamination getting through. A TenCate Polyfelt TS non-woven geotextile lies beneath the film for protection. An RE grid directly on top of the film prevents the sand from sliding. The same RE grid is also incorporated as reinforcement in the next two to three sand layers.
The project was carried out by Joosten Concepts partners, Molhoek-CCT and Loonbedrijf Van Etten. Materials were supplied by Joosten Kunststoffen in collaboration with TenCate and Tensar.
A business enquiry for Joosten Groep? Get in touch
Who worked on Botlekbrug
- RE Geogrids
TensarMentioned in Use of pumice in reinforced soil construction for rail is unique in the Netherlands - Polyfelt TS non-woven geotextileTenCateMentioned in Use of pumice in reinforced soil construction for rail is unique in the Netherlands
- carried out by
MolhoekMentioned in Pumice used in reinforced soil structure for railway is unique in the Netherlands - carried out byLoonbedrijf Van EttenMentioned in Pumice used in reinforced soil structure for railway is unique in the Netherlands
- materialsJoosten KunststoffenMentioned in Pumice used in reinforced soil structure for railway is unique in the Netherlands
- designGeologicsIn this story
- contract partner
Croonwolter&drosMentioned in Croonwolter&dros and Elinex deliver Botlek Tunnel emergency power system through to 2035
Keep following this
Get an email when a new story is published. No account needed.
- ProjectBotlekbrug
- SubjectSpecials
- CompanyGeologics
- CompanyJoosten Groep
- CompanyTensar International BV
- CompanyMolhoek Infratechniek