Successful strengthening operation on viaduct on the A7

Text Roel van Gils Image Van der Jagt Groep

Van der Jagt Groep moest in twee fases van elk vijf weken in totaal 50.000 gaten boren en daarin de wapeningsstekken verlijmen.
Van der Jagt Groep moest in twee fases van elk vijf weken in totaal 50.000 gaten boren en daarin de wapeningsstekken verlijmen.

50,000 holes drilled for 15 kilometres of additional reinforcement

During an inspection in 2022, the supports of the viaduct carrying the A7 over the Noordhollandsch Kanaal near Purmerend were found to have weakened. To allow traffic to use the structure safely again, without weight restrictions, the bridge was strengthened as a matter of urgency. Van der Jagt Groep was brought in to relocate the expansion joints, drill no fewer than 50,000 holes and bond more than 15 kilometres of reinforcing bars into place. A massive job completed in an extremely short time.

At peak times, more than 70 Van der Jagt Groep specialists were working on site at the same time.

The A7 is a major transport artery in the north of the Netherlands. Every day, many thousands of vehicles cross the viaduct near Purmerend. “Bouwcombinatie Savera promised to complete the strengthening operation in an extremely short period of just five months,” says Adriaan van der Jagt. “Given the amount of work involved, that seemed pretty ambitious. But when a job is unusual, extensive, large or deep, we are the right people for it. We were involved from the outset to work out the creative solution and plan the work as efficiently as possible, while keeping the bridge open to traffic in both directions throughout the works, albeit with narrowed lanes.”

The bridge supports were strengthened in two sections, one for each carriageway.

Right down to the last hole

Work on both carriageways took place between 1 April and 1 September 2024. The bridge supports were strengthened in two sections, one for each carriageway. Van der Jagt Groep had two five-week phases to drill a total of 50,000 holes and bond reinforcement bars into them. The bars ranged from 12 to 32 mm in diameter and from 25 to 150 centimetres in length. “There are very few companies in the Netherlands able to take on a contract of this size,” says Adriaan. “That is precisely where our strength lies. We assign a project team and literally go right down to the last hole, contributing from the planning stage through to successful delivery. That is the added value of Van der Jagt Groep. At peak times, more than 70 of our specialists were working on site at the same time. We first lowered the edges of the carriageway and the central reservation before strengthening them with new anchors. This was to ensure sufficient cover after the overlay was applied.”

In addition to drilling the holes and bonding the anchors, Van der Jagt Groep also sawed open and removed all sixteen of the bridge’s expansion joints.

Taking the burden off the client

In addition to drilling the holes and bonding the anchors, Van der Jagt Groep also sawed open and removed all sixteen of the bridge’s expansion joints. “The beams were then shortened slightly so the new joints could be installed in sound concrete. Structurally, there was room to do this,” Adriaan explains. Van der Jagt Groep bonded the last reinforcement bars into place at the end of August. “We look back on a project that went perfectly and a great collaboration with Bouwcombinatie Savera. These projects are right up our street. As a partner to the construction consortium, we take the entire scope off its hands, from A to Z, so it has nothing else to worry about and can be confident of a solid end result.” During the planning stage, Adriaan was invited by Savera to explain the work to the Minister of Infrastructure and Water Management. “The photo of the minister holding our drilling machine was a hit on social media.”     

At the end of August, Van der Jagt Groep completed the final work on the project.

A business enquiry for Van der Jagt Groep? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeExtending the life of roads and civil engineering structures
  • SubjectSpecials
  • CompanyVan der Jagt Groep
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.