Second lock at Eefde to improve access to the Twentekanalen

The existing lock at Eefde, on the Twentekanaal just beyond its junction with the IJssel near Zutphen, is facing a capacity problem. To meet the expected growth in waterborne transport, Rijkswaterstaat has commissioned the addition of a second lock chamber, suitable for more heavily laden vessels. The second lock chamber will also make the situation less vulnerable in the event of maintenance, emergencies or problems caused by low water levels.
The main contractor is ‘Lock to Twente’ (L2T), a partnership between Mobilis (civil engineering), Croonwolter&dros (technical installations) and TBI PPP. The consortium began preparatory work at the end of 2017. Construction of the second chamber began in early 2018, and the first vessels are expected to pass through the lock in mid-2020.

Voorbij Funderingstechniek installs anchors.
Technical challenges
The challenges involved in a comprehensive TBI project of this kind are primarily technical: connecting an entire structure to the waterway. This was a key reason for L2T to work with Voorbij Funderingstechniek, the versatile partner in load-bearing capacity. Harm Wammes, project manager at Voorbij Funderingstechniek, explains: “On projects this complex, it is crucial to get all parties round the table at an early stage to share knowledge and expertise. This is beneficial not only for the construction work, but also offers significant design advantages. We used the existing design parameters as a starting point and worked on the design and its optimisation to arrive at the best solution.”

Voorbij Funderingstechniek.
Prepared for anything
“At the end of October 2017, we carried out preliminary piling trials,” Harm continues. “These enabled us to assess noise levels, vibrations and the drivability of the sheet piles, as well as make a more accurate forecast of production rates. By optimising the sheet-pile design in the lock chamber, we were able to save a considerable amount of concrete. We started installing sheet piles using several machines in January 2018. We invested heavily in our fleet over the past year: the Hitachi Sumitomo SCX 1000 was delivered in June 2018 and put straight to work on this project. It was used to install tubular piles weighing up to 25 tonnes and sheet piles up to 26 metres long, with good results. For this project, we supplied and installed around 2,500 linear metres of sheet piling, complete with anchors and walings. While installing the sheet piles, we encountered obstructions, most likely construction debris from the existing lock. As a result, the piles could no longer be driven to the required depth using vibration, so we switched to impact driving with an IHC hammer. A mobile noise barrier was deployed to minimise disruption to the surrounding area. In this way, like Rijkswaterstaat, we are aiming to complete the project within the limits for environmental nuisance, sustainability and safety.”

Installing sheet piles with a noise barrier.
Sustainable and safe
“Our focus is on delivering technically and economically sound structures. Voorbij Funderingstechniek offers a complete solution covering design, project management and construction, with due regard for the environment and in anticipation of local conditions. The Eefde Lock Expansion project is an ideal opportunity to further promote our TOVF safety programme. TOVF stands for Trots Op Veilig Funderen, meaning ‘proud to build foundations safely’, and safety is a top priority for us. Alongside the safety and health of our people, sustainability is also high on our agenda. The new lock chamber has been designed to be energy-neutral. The technical installations will be energy-efficient, and practically all the sheet piles used are being transported by water. The energy needed to operate the second lock chamber will be generated by solar panels. The existing lock at Eefde is a listed monument and a landmark in the landscape. I am pleased to say that the second lock will be very special too,” Harm concludes.
A business enquiry for Croonwolter&dros? Get in touch
Who worked on Sluis Eefde
- contractors' joint ventureLock to Twente (L2T)Mentioned in Specialist earthworks for the construction of a second lock chamber at Eefde
- PMS software
SoltegroMentioned in A good performance measurement system must be stable, reliable and future-proof - financingTBI PPPMentioned in Mobilis and Croonwolter&dros consortium built new lock and is renovating existing one
- clientRijkswaterstaatMentioned in Mobilis and Croonwolter&dros consortium built new lock and is renovating existing one
- temporary pumping installations
VanderkampMentioned in Combining data and expertise to develop an optimal emergency plan
Keep following this
Get an email when a new story is published. No account needed.
- ProjectSluis Eefde
- SubjectSpecials
- CompanyCroonwolter&dros
- CompanyMobilis
- CompanyVoorbij Funderingstechniek