Mobilis and Croonwolter&dros consortium built new lock and is renovating existing one

Mobilis and Croonwolter&dros consortium built new lock and is renovating existing one

In 2016, the consortium ‘Lock to Twente’, comprising TBI companies Mobilis (civil engineering), Croonwolter&dros (technological solutions) and TBI PPP (financing), won the contract to build a second lock at Eefde.

Lock to Twente (L2T) is responsible for pre-financing, design and construction. The contract also includes 27 years of maintenance of the new lock.

Preparatory work for the expansion began in 2017, and construction started in January 2018. Ships have been using the new lock since April 2020. The second lock chamber at Eefde reduces waiting times for vessels and makes access to the Twente Canals less vulnerable to maintenance work and faults. The new lock can accommodate class Va vessels, the largest type of vessel permitted after the Twente Canals are enlarged. We speak to Paul Schaap, DBM Manager for EPC L2T (representing TBI), and Robbert Visser, Project Manager for the client, Rijkswaterstaat.

Smart choices make Eefde Lock safe and future-proof

“The new lock chamber has now been completed and brought into service. We are currently in the second phase, renovating the old lock,” Paul begins. Robbert adds: “The remaining work on the new lock involves completing the buildings and installing new sheet piles in the approach harbours.” L2T made a strong impression in the tender with its innovative and sustainable choices. Robbert explains: “For example, we proposed a sector gate. It is no cheaper to build than two mitre gates, but it is considerably cheaper to maintain.” Paul says: “A sector gate of this size is unique in the Netherlands. It is located on the canal side of the lock complex and lies flat on the bottom when the lock is open. From that position, it swings upwards when the lock closes. The gate also works under very high water pressure, for example if the other gate loses its ability to hold back water due to damage. This can result in large differences in water levels. In an emergency in the lock, this feature helps ensure safety.” The new lock chamber has been designed to be energy-neutral. Robbert says: “The technical installations will be energy-efficient. The energy still required to operate the lock chamber will be generated at the lock complex using solar panels.”

Read the full article here

Een zakelijke vraag aan Mobilis? Neem contact op

Wie aan Sluis Eefde werkte

  1. technische installatiesCroonwolter&drosGenoemd in Second lock at Eefde to improve access to the Twentekanalen
  2. civiele techniekMobilisGenoemd in Second lock at Eefde to improve access to the Twentekanalen
  3. plaatst verankeringenVoorbij FunderingstechniekGenoemd in Second lock at Eefde to improve access to the Twentekanalen
  4. aannemerscombinatieLock to Twente (L2T)Genoemd in Specialist earthworks for the construction of a second lock chamber at Eefde
  5. financieringTBI PPPIn dit verhaal
  6. opdrachtgeverRijkswaterstaatIn dit verhaal
  7. bekistingsspecialistDoka NederlandGenoemd in The first lock with a tilting gate
  8. tijdelijke pompinstallatiesVanderkampGenoemd in Combining data and expertise to develop an optimal emergency plan

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectSluis Eefde
  • OnderwerpBouwMat
  • BedrijfTBI PPP
  • BedrijfRijkswaterstaat
  • BedrijfMobilis
  • BedrijfCroonwolter&dros
  • BedrijfEPC Groep
Deel dit artikel

Volgen op Grond/Weg/Waterbouw Nederland

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.