Schiphol | Completion of the Dual Taxiway System (VDR) project: flyover

This year, the flyover being built as part of the Completion of the Dual Taxiway System (VDR) project on the south side of Schiphol Centrum will come into view.
Heijmans’ design and construction contract includes building a 250-metre-long, 60-metre-wide flyover across the A4, alongside the existing flyover. In addition to crossing this busy motorway, the new flyover will cross several other vital arteries, including two ProRail railway tunnels, a public transport tunnel, the road link between staff car park P30 and Schiphol Plaza, and a major cable and pipeline route, the aorta of Schiphol. It is therefore a complex undertaking that ‘connects’ in both a literal and figurative sense.
With the additional taxiway, Schiphol aims to make the airport even safer, reduce waiting times for taxiing aircraft and simplify the situation for air traffic control. “This issue has been on the agenda for many years,” says Derk Stolwijk, project manager at Schiphol Projects. “Viewed from above, you can see that the Alfa and Bravo taxiway system is fully duplicated. Aircraft travelling in opposite directions never meet. The missing section is taxiway Quebec across the A4, between the Kaagbaan and Zwanenburgbaan. Air traffic control always has to direct aircraft traffic here. This bottleneck also causes congestion on the ground when certain runways are in use. The only solution is to build a new flyover.”
Integrated design
Given the wide range of stakeholders involved, Heijmans Infra produced an integrated design based on a preliminary design drawn up by RHDHV. “The design and construction have been perfectly coordinated,” says Barry de Gier, construction manager at Heijmans. “During the design phase, we scrutinised many aspects to ensure that the project would always be buildable. That pays dividends later on. The requirements and specific characteristics of all stakeholders were also identified at an early stage.” Stolwijk gives an example: “A support for the new flyover is being built between the two ProRail tunnels. Heijmans must contend not only with the extremely limited clearance between them, just 1,720 millimetres, for installing the large foundation piles, which have a diameter of 830 millimetres, but also with strict limits on deformation of both tunnel bores. The rails in the old tunnel are fixed directly to the floor. Movares has developed a monitoring system to track movement in both tunnels across six tunnel sections. In response to these requirements, Heijmans Infra decided to use a different type of foundation pile to reduce the risks. The first row of cased screw piles, a ground-neutral technique, has now been successfully installed.”

Schiphol-HUB
The new flyover will rest on two abutments, three supports (pier walls) in the A4 and six supports on land. A stability core is also included. “We largely opted for a proven construction method with straightforward staging, and deliberately avoided pioneering in such a complex environment with so many stakeholders,” De Gier continues. “By carrying out much of the work in advance, such as preparing the reinforcement and formwork, we can schedule critical activities at weekends rather than during the day on weekdays, with all the resulting road closures. We can also make good use of Schiphol-HUB, a large off-site construction area.” Stolwijk adds: “The site is part of the project organisation that coordinates all major projects at the airport. Logistics are managed from here, and other major projects can use the site too. As it happens, it is strategically located for VDR at the head of the Kaagbaan, close to the new flyover.”
Mikado for experts
Heijmans is making good use of Schiphol-HUB. “We incorporated a great deal of repetition into the design of the 60-metre-long pier walls, each consisting of nine columns,” De Gier explains. “That justified a prefabrication process. At the off-site construction area, the steel formwork for the pier walls was fully prepared and even fitted with reinforcement. This meant we could install the formwork in just one weekend and had relatively little reinforcement to place on site. As a result, there were far fewer disruptive closures of the A4. On Friday evening there was nothing to see, and by Monday morning there was 60 metres of ‘Mikado for experts’. The concrete was also poured at night. Each pier wall contains around 265 m3 of concrete. Across the entire project, the total is more than 20,000 m3. That is also why we set up a mobile concrete plant at Schiphol, to keep transport distances as short as possible. This contributes to our sustainability objectives.”
Logistics operation
Heijmans expects to have completed all the supports by early May; the pier walls in the A4 will already be finished by mid-March. The deck will then be built using precast beams. “It’s a huge logistics operation,” De Gier acknowledges. “There are a great many beams. Each span, 60 metres wide, consists of 40 beams spanning 22 to 25 metres. There are 11 spans in total. The flyover is scheduled to be structurally complete in October 2021. After that, the taxiway will be built, with special asphalt, markings, lighting and cabling. Many of the associated works will also be carried out in parallel. The new flyover will be commissioned after handover.”
Question about this story? Ask your question
Who worked on it
Completion of Dubbele Rijbaanstelsel (VDR)
- construction and design briefHeijmans
- monitoring systemMovares
Keep following this
Get an email when a new story is published. No account needed.
- ProjectCompletion of Dubbele Rijbaanstelsel (VDR)
- ThemeExtending the life of roads and civil engineering structures
- SubjectSpecials