Keeping the cofferdam dry during tidal culvert construction
Text Roel van Gils Beeld Henk van Tongeren Water & Techniek

Alongside the strengthening of the Lauwersmeerdijk, a number of nature projects are being carried out to improve the ecological water quality and natural environment of the Wadden Sea. One of these is the creation of the Marnewaard tidal area, which involves building a tidal culvert through the Lauwersmeerdijk. Henk van Tongeren Water & Techniek is keeping the cofferdam dry.
In November 2023, Combinatie Waddenkwartier approached Henk van Tongeren Water & Techniek to turn the dewatering advice into a practical solution for the tidal culvert construction. “The cofferdam is about 100 metres long, 13 metres wide and 6 metres deep,” says Jorim Beishuizen, operations manager at Henk van Tongeren Water & Techniek. “Our job is to keep the cofferdam nice and dry, so that Combinatie Waddenkwartier can build the tidal culvert ‘in the dry’.”

Deep wells
Henk van Tongeren Water & Techniek installed a dewatering system comprising 52 deep wells. “That is quite a lot given the size of the cofferdam,” Jorim admits. “However, half of them serve as a buffer and provide a safety measure for risk management. The wells are 15 metres deep, with the pumps hanging about 13 metres below ground level. We installed 26 submersible pumps to pump groundwater (salt water, ed.) to the surface and discharge it into the sea on the other side of the cofferdam.” The total capacity for the cofferdam is 50 m3 per hour. “The electric pumps are powered by two sets of generators running on HVO 20 fuel, and are equipped with an emergency power supply. They are controlled via a pump control cabinet that we can monitor remotely. In fact, we can even switch the pumps on and off remotely or adjust the water level.”
Complex surroundings
Henk van Tongeren Water & Techniek’s dewatering system has been running since the start of the summer holiday and, according to Jorim, will be in operation for a total of one year. “Installing the wells took about five weeks and went entirely according to plan. It did require careful coordination with the many stakeholders, because the site is quite complex and is also used periodically by the Ministry of Defence. From a scheduling perspective, it was therefore a challenge to coordinate all the work. But we managed that too, in close consultation with Combinatie Waddenkwartier. Our people are used to this kind of challenge and enjoy projects where they can make full use of their expertise. That is one of our strengths: getting involved from the early stages to help devise the best possible dewatering solution. For now, our task is to monitor the system and carry out maintenance from time to time, so that the consortium can build the tidal culvert without disruption and with dry feet.”
Een zakelijke vraag aan Henk van Tongeren Water & Techniek? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeUnderground construction
- SubjectSpecials
- CompanyHenk van Tongeren Water & Techniek