From wastewater treatment plants to wastewater pumping stations
Text Roel van Gils Image VOBI Infra

Two new pumping stations connect the region to the future
The completion of the AWS Zwanenburg project, construction of wastewater pumping stations, marks an important step in modernising the wastewater network in the Haarlem region. Two ageing wastewater treatment plants (AWZIs) have been replaced by modern wastewater pumping stations (AWTGs). The project presented a number of technical challenges, particularly due to unforeseen circumstances. Nevertheless, VOBI Infra and the Rijnland Water Authority overcame these obstacles very efficiently.
The project centred on Heemstede and Haarlem-Schalkwijk, where the two ageing wastewater treatment plants were replaced by modern pumping stations. These AWTGs pump wastewater under pressure to the existing, now expanded, treatment plant in Zwanenburg, some 10 kilometres away. Whereas wastewater was previously treated at three sites, it is now treated centrally at a single location. This not only improves efficiency, but also delivers significant savings in energy and maintenance costs.

Combining disciplines
VOBI Infra was selected through a MEAT tender, in which risk management, sustainability and collaboration were among the decisive factors. “We have been active in projects of this kind for decades,” says managing director Bastiaan Blok, who also served as project manager on this project. “Our strength lies in combining civil engineering, mechanical engineering and electrical engineering. Because we have some of these disciplines in-house, including temporary pumping and pipework systems, we can respond quickly and adapt flexibly to challenges.”
A rollercoaster
And there were challenges. “An inspection of the existing sewer in Haarlem-Schalkwijk revealed that the reality differed considerably from the available as-built drawings,” says Blok. “The pipe, which the drawings showed as being supported on foundations and stable, was in fact not piled, resulting in subsidence of 30 to 40 centimetres and giving it the profile of a ‘rollercoaster’. This called for a creative solution, because the new AWTG had to be connected to an existing pipe prone to settlement without itself settling.”

Small integrated project team
In close collaboration with the Rijnland Water Authority, an innovative design using articulated connectors was developed by a small integrated project team. “This solution allows future settlement to be accommodated without damaging the connection. Moments like these show how important good collaboration is,” says Blok. “You need each other to arrive at a robust and reliable solution.”
Sharing knowledge
VOBI Infra built the AWTGs in parallel. “Although we started a little earlier in Heemstede, in October 2022 to be precise, work in Haarlem-Schalkwijk followed in spring 2023. By carrying out the projects one after the other, like a production line, we were able to transfer knowledge and experience efficiently. The two pumping stations have a similar design, but differ in capacity. The Heemstede pumping station has a capacity of 1,500 m3/hour and a 710 mm diameter rising main, while the Haarlem-Schalkwijk station reaches a peak of 2,000 m3/hour and is connected to a rising main of around 800 mm in diameter.”

Engineering underground
Although above ground only a modest building is visible, a 7 by 7 metre, 5-metre-high ‘hut’, an impressive technical installation lies beneath it. Deep concrete chambers, extending up to 10 metres below ground level, are divided into two compartments. The dry section houses the pumps and pipework, while the wet section serves as the receiving chamber for incoming wastewater. The superstructure is sustainably built in timber and features a sedum roof and solar panels. VOBI Infra successfully completed and handed over both AWTGs to the Rijnland Water Authority on 3 July 2025.
Question about this story? Ask your question
Who worked on Project Zwanenburg
- specialist supplier
AVK NederlandMentioned in The benefits of a specialist supplier in wastewater treatment - mechanical engineering worksRWB WaterMentioned in The benefits of a specialist supplier in wastewater treatment
Keep following this
Get an email when a new story is published. No account needed.
- ProjectProject Zwanenburg
- SubjectSpecials