Foundations / Site investigation

Kandt and BAM Infra Civiel join forces for Trekvlietbrug in The Hague

Text Susan PeekImage Kandt Aannemings- en Funderingsbedrijf BV

Damwandplanken worden ingehesen tijdens kortstondige verkeersstops op reguliere werkdagen.
Damwandplanken worden ingehesen tijdens kortstondige verkeersstops op reguliere werkdagen.

A new underpass for cyclists and pedestrians is being built beneath Trekvlietbrug in The Hague. It will remove a dangerous junction and provide a safe route towards the city centre. But building beneath a busy arterial road is no easy task. 

A large-scale infrastructure project like this calls for smart decisions and close collaboration. The construction team, with BAM Infra Civiel as main contractor and the Municipality of The Hague as client, is working with specialist partners to carry out a short, intensive closure of Mercuriusweg. “That 9-day road closure is when everything comes together,” says Bastiaan Verheul, head of the operations office at Kandt Aannemings- en Funderingsbedrijf.

A section of the sheet piling has been installed 17 metres from the quay to create a sand platform for moving the prefabricated deck into position.

Collaboration from the design stage

The project was brought to market as a construction team project two years ago. The Municipality of The Hague was specifically looking for a contractor who would contribute from the outset to ensuring the design was buildable and minimising disruption. BAM Infra Civiel was commissioned to develop the design further in collaboration with the municipality. Foundation specialist Kandt BV contributed its expertise from the design stage.

“Mercuriusweg is an important route into the city,” says Verheul. “The original design called for a lengthy phased approach that would cause considerable traffic disruption: two extended closures of half the road. BAM proposed a single full closure lasting nine days, during which the underpass could be built at the junction with Mercuriusweg. The road could then reopen straight away. That was smarter, safer and caused considerably less disruption. This won BAM the contract, and we joined the construction team as its foundation partner to develop the plan further and make it buildable.”

Fluidisation is used when installing the sheet piles to prevent vibration nuisance.

Extensive foundation works

For Kandt, this involved a wide range of works. “We installed around 250 metres of permanent sheet piling and 100 metres of temporary sheet piling,” says Verheul. “We used fluidisation to limit vibration nuisance in the surrounding area. That is crucial in a built-up urban environment. One unusual feature was the temporary sheet pile wall, 17 metres from the existing quay. This area was filled with sand, creating space to move the prefabricated deck into position during the closure.”

Kandt also installed 60 permanent and 20 temporary LeKa piles. “Design optimisations reduced the number of piles, making the solution more sustainable. The temporary piles were drilled at the prefabrication site. After the bridge deck has been moved into position, they will be drilled out and reused on another project later this year.” Kandt is also removing 65 old piles beneath the existing quay that run across the route of the new cycle path. “BAM is demolishing that section of the old quay, and we are clearing the way for the new underpass and quay alignment. The piles are 18-metre-long precast concrete piles, installed at inclinations of 3:1 and 4:1. Extracting them takes skill.”

A foundation rig is set up on a bridging structure over a cable and pipe corridor.

Smart solutions for complex conditions

The main challenge lay in the existing surroundings. “The new sheet pile alignment crosses existing grout anchor bars at several points. At the points of conflict, we drilled through the anchors at a depth of 7 metres using a special technique to make room for the new alignment. This requires careful preparation and execution.” Traffic stops were used for work within the traffic fall zone. “That is essential for the safety of our people and road users.”

The underpass and part of the quay renewal have a total construction period of one year. Almost all foundation works, including installing sheet piles, LeKa piles and grout anchors, and extracting piles, took place on normal working days. Only the section crossing Mercuriusweg was carried out during the 9-day road closure.

Bridging structures and collaboration in the construction team

Another challenge was protecting underground cables and pipes from imposed loads. “Together with BAM, we designed and built bridging structures so that traffic on Mercuriusweg could keep flowing for as long as possible while the infrastructure was protected. Solutions like these are developed step by step through collaboration in the construction team.”

Verheul stresses the importance of this construction team approach. “It is not just about carrying out what is on paper, but about identifying and resolving risks together. From the outset, we sat down with BAM and the municipality as one team to prepare everything down to the last detail. During those nine days, every operation has to dovetail seamlessly: we install the sheet piles, piles and road anchors, then, halfway through, BAM moves the bridge deck into position. The alignment is then backfilled and asphalted so traffic can get moving again.”

The value of preparation

“To make sure everything is in place during those nine days, months of detailed planning have gone into the work. Despite the many disciplines involved, the plan has been set up so that everyone agrees it is achievable. But that is only possible if you work together in a construction team, tackle risks in advance and incorporate integrated solutions into the design. That is where we add value as a specialist: making sure the plan can actually be delivered as intended.”     

A business enquiry for Kandt Aannemings- en Funderingsbedrijf BV? Get in touch

Who worked on it

Trekvlietbrug in Den Haag

  1. foundation partnerKandt
  2. main contractorBAM Infra Civiel
  3. clientmunicipality of Den Haag

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectTrekvlietbrug
  • ThemeViable projects and strong collaboration
  • SubjectFoundations / Site investigation
  • CompanyKandt Aannemings- en Funderingsbedrijf BV
  • CompanyBAM Infra Civiel
  • Companymunicipality of Den Haag