Complex steelwork meets precision engineering

The heaviest mobile cranes were deployed to lift the lock gates.
The heaviest mobile cranes were deployed to lift the lock gates.

“Exceptional, exciting and complex.” That is how Harm Wattel, Business Development Manager at ASK Romein, describes the delivery of the lock gates for the flood barrier at Den Oever. It was up to the team to manage the project from start to finish.

Protection against extreme high water

The lock gates were built at ASK Romein’s own site in Vlissingen.

The new flood barrier at Den Oever protects against extreme high water in the Wadden Sea. In such conditions, the lock keepers close the gates to protect the hinterland. “The gates also provide a permanent flood defence and safe passage for vessels,” Wattel explains. “The project was completed in accordance with execution class 4, which means it had to meet the most stringent quality requirements.”

Moving seamlessly

The Afsluitdijk renewal project is a good example of how ASK Romein’s expertise comes into its own. A leading player in the Dutch and Belgian steel construction markets, and increasingly further afield, the company has everything it needs to deliver the engineering, manufacture and execution of steel construction projects flawlessly. All these capabilities came into play in the contract for the two lock gates. According to Harm, the design, construction and installation of the gates sat at the interface between heavy steelwork and precision engineering. “On the one hand, you have heavy welding and a substantial structure, while on the other, the entire assembly has to turn with great precision and be 100% watertight. We are also responsible for the protective coating and guarantee that maintenance requirements will be minimal for the next 25 years.”

A tense moment

The lock gates were built at ASK Romein’s own site in Vlissingen. From there, the whole structure was transported by water to Den Oever, ready for installation in the flood barrier. Although ASK Romein’s staff are used to projects of this complexity, the work is always a challenge. “The gates are so-called mitre gates: when closed, they meet in a point facing outwards. Each weighs 70 tonnes and measures 8 metres wide by 11.5 metres high. We used the heaviest mobile cranes to lift them, one weighing 650 tonnes and the other 130 tonnes. The limited space we had to work in was what made it particularly challenging.”

Proud

Looking back on the entire project, Wattel is satisfied and, above all, proud. “The best thing about our work is that, on projects like this, we can meet the highest quality requirements with specialist steelwork. The combination of technical expertise and our people’s passionate commitment leads to maximum customer satisfaction time and again. That is ASK Romein’s strength!”   

A business enquiry for ASK Romein? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeExtending the life of roads and civil engineering structures
  • SubjectSpecials
  • CompanyASK Romein
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.