Smart integration strategy for testing traffic and tunnel systems

Het testen van de installaties in de Hollandtunnel gebeurt vanaf diverse locaties.
Het testen van de installaties in de Hollandtunnel gebeurt vanaf diverse locaties.

At the time of writing, construction consortium BAAK is still carrying out the immersion operation for the Maasdeltatunnel, while the traffic and tunnel systems for the A24 Blankenburgverbinding are already being physically tested on site. This smart integration strategy, using a loop around the outside via the Maeslantkering, is saving a great deal of time. We speak to Richard de Klerk, TTI Manager for the Blankenburgverbinding on behalf of Rijkswaterstaat, about this unique approach.

A loop around the outside

A look inside the Hollandtunnel.

Immersing the second and final tunnel section of the Maasdeltatunnel marks the completion of the civil engineering works. It completes the new link, which from 2024 will connect the A20 near Vlaardingen with the A15 near Rozendaal. “All in all, it is also an interesting project from an installation engineering perspective,” says De Klerk. “As well as the civil engineering works, the traffic system also needs to be connected to the rest of the road network in the south-west of the Netherlands. And there are two tunnels along this relatively short route. The Hollandtunnel is only half the length of the Maasdeltatunnel, but has exactly the same facilities. This is thanks to the standardised tunnel legislation we have in the Netherlands. That is a great asset, as it means fewer discussions during design and construction. We are making good use of that in this project.”

A single tunnel system

As the new A24 is a continuous road, both tunnels have the same cross-section, with three lanes in each of two tubes. “From a traffic management perspective, the route will be controlled centrally from the Verkeerscentrale Zuidwest-Nederland, and locally from the Dienstgebouw-Zuid at the Maasdeltatunnel if necessary,” De Klerk explains. “Physically there are two tunnels, but from a traffic management perspective they are treated as a single tunnel system in one software environment.” As mentioned, the tunnels will be fitted with exactly the same systems. “Given the progress of the civil engineering works, with the Hollandtunnel due for completion before the Maasdeltatunnel, the decision was made to install and test the systems in the cut-and-cover tunnel first, then install the identical systems in the immersed tunnel after the summer.” The software environment for both tunnels will be housed in a computer room in the Maasdeltatunnel Dienstgebouw-Zuid.

Both tunnels will be fitted with exactly the same systems.

Maeslantkering

The systems in the Hollandtunnel are being tested from several locations. Testing begins at a temporary control point at the Hollandtunnel, then continues from both the Maasdeltatunnel Dienstgebouw-Zuid and the traffic control centre. “As other tunnels are also controlled from there, we want to minimise disruption during testing as much as possible. Since the civil engineering works on the A24 are not yet complete, we are temporarily routing the fibre-optic network in a loop via the Maeslantkering, using an existing Rijkswaterstaat network,” De Klerk explains. “This makes it look as though we are going through the Maasdeltatunnel. That way, we can bring all the network facilities and equipment in the Hollandtunnel online and test them before the immersed tunnel is ready, saving valuable time. Any faults that come to light now can be resolved, so they will not recur when the Maasdeltatunnel is tested. The systems are identical, after all.” 

A loop in the fibre-optic network via the Maeslantkering allows all the network facilities and equipment in the Hollandtunnel to be brought online and tested before the Maasdeltatunnel is ready.

Testing at the Hollandtunnel is now in full swing. De Klerk: “Around the summer, we will also use the same loop to test the traffic lights, emergency cross-passages and boom barriers on the access roads to the Maasdeltatunnel. We expect to be able to test the Maasdeltatunnel, and therefore the entire A24 Blankenburgverbinding, from October-November this year, using the permanent network, of course. That will be the end of the loop around the outside.”   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeUnderground construction
  • SubjectRoad construction
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.