Rail infrastructure specialist undertakes foundation work for Wormerveer embankment repairs

With more than forty years’ experience installing sheet pile and piling systems in a wide range of locations and conditions, Kandt BV is not one to shy away from a challenge.
That was also the case on this project in Wormerveer, where Kandt installed a 150-metre steel sheet pile wall at a site with difficult access. Commissioned by main contractor K_Dekker bouw &infra, the company restored and stabilised the railway formation and embankment alongside the track for ProRail, after which the railway line was reopened.
“Installing sheet piles is, in itself, routine work for our company,” says Bastiaan Verheul, project manager at Kandt. “But this project was a little different. The limited space outside the railway boundary, the fact that the site was accessible only by rail and the time pressure of the planned possession all made it challenging. But our approach, knowledge and expertise, combined with our specialist plant, were perfectly suited to the job.”

Good preparation is half the job
“Every project is unique in terms of its circumstances, complexity and challenges. But we always provide a suitable solution. Good preparation is essential,” Verheul continues. “During the tender phase, we contributed ideas on the best way to approach this project. Identifying risks early and helping to develop solutions pays dividends at a later stage in the process.” The site was therefore carefully surveyed, well-considered plans were drawn up, the worksite was set up and the logistics around it were worked out. “That was where the main challenge lay,” says Verheul. “Our experience in railway works came in very useful.”
Everything by rail
“In the period leading up to the possession, both main contractor K_Dekker and the Kandt team were busy carrying out the preparatory work. An access point was set up at an existing level crossing, 900 metres from the worksite, from where the site could be reached by rail. The route for transporting equipment and materials ran partly alongside a station platform. At the worksite, there was a ditch on one side of the railway embankment, with dense housing beyond it, and a field on the other side that was inaccessible. The required materials and equipment were brought from the access point along the track during a period when no trains were running. We have our own rail equipment for this.”

Safe and efficient
The work was carried out during a 104-hour possession at the end of February. “That may sound like a relatively long period with no trains running,” says Verheul, “but it is crucial that the successive activities carried out by different disciplines do not interfere with one another. It places considerable demands on people and machinery when they have to keep working for such a long time. The equipment must also be suited to the task. Kandt’s KSC926 is a specialist machine that could be transported from the access point to the worksite using our own rail equipment. “Despite the limited space and steep embankment, the sheet piles were installed swiftly, efficiently and safely.” Verheul says good cooperation between the parties contributed to the end result. “Everyone working on site, from ProRail and main contractor K_Dekker to the other subcontractors and stakeholders such as the cable and pipeline manager, the earthworks contractor and the overhead line team, worked together constructively. Each brought the expertise required in their own specialist field.” Verheul concludes: “It is good to see everyone working towards a shared goal during a possession, with a greater willingness than usual to help one another. That means you can get the work done on time and within budget, and achieve a great result that we can all be proud of.”
A business enquiry for Kandt Aannemings- en Funderingsbedrijf BV? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeUnderground construction
- SubjectRoad construction
- CompanyKandt Aannemings- en Funderingsbedrijf BV