BUKO ensures access and safety during maintenance of the Prins willem-Alexanderbrug (N323)
Text Susan Peek Beeld Vivo Fotografie & Drone Inspecties

The Prins Willem-Alexanderbrug on the N323 between Echteld and Beneden-Leeuwen is the only concrete cable-stayed bridge in the Netherlands. Major maintenance is being carried out in several phases between 2025 and 2029. After the asphalt was renewed in 2024, the expansion joints were replaced in 2025 as part of the GO programme. They had reached the end of their service life after more than 50 years. BUKO provided the temporary traffic management measures on behalf of contractor Maurer.
Extensive preparations
According to project coordinator Matthijs Spies, the project required lengthy preparation. “Calculations were made in consultation with the province, contractor and Rijkswaterstaat to ensure traffic flow and safety,” he says. BUKO Bereikbaar was also involved from the outset to communicate with local communities and road users.

Operational approach
Replacing the expansion joints meant major works on a busy arterial route. “We couldn’t close the bridge completely,” says Spies. “So we opted for a 2-0 system, with traffic in both directions routed over one carriageway. Nearly 3 kilometres of barriers separated the traffic flows.”
The measure required three weekend closures: one to set up the system, one to switch the traffic flow and one to complete the works and carry out additional maintenance, such as replacing a joint above the railway flyover. “We even finished ahead of schedule during the first weekend,” says Spies.
BUKO provided all the temporary traffic management measures: barriers, road markings, lighting and removal of the safety barriers. “We always work with reliable partners,” says Spies. “Good coordination is crucial to getting everything in place safely and on time.” Camera masts from BUKO Waakt enabled the province and emergency services to monitor the works live and intervene immediately if necessary.
Digital capability
Digital technology also played a key role. Project leader Matthijs Beelen says: “With BUKO Bereikbaar, we researched in advance who uses the bridge and where they travel from.” Based on these insights, BUKO launched a digital campaign. “Road users were proactively informed via social media and push notifications. Digital beacons on the bridge sent voice messages to Flitsmeister to alert motorists in good time to the planned closures. We also monitor all traffic flows around the diversions,” says Beelen. “This will enable the province and road authority to plan more effectively in future.”
Collaboration and pilot project
The project serves as a dress rehearsal for the major maintenance planned for 2026 and 2027. “We really see this as a pilot, giving us an even better understanding of what works and what could be improved,” says Spies.
Both are proud of the collaboration and preparation, which have proved their worth in practice. “Everyone knew their role and was willing to contribute ideas,” says Spies. Beelen adds: “The lengthy preparation is paying off in the way traffic behaves and responds. Everything is being followed up properly, proving that the plan was well thought through.”
This project demonstrates BUKO’s strengths: taking the burden off clients, responding quickly and ensuring accessibility through physical and digital services. “It’s great to hear clients say: everything is running brilliantly and has been arranged down to the last detail,” Beelen concludes.
A business enquiry for BUKO Infrasupport? Get in touch
Who worked on it
Prins Willem-Alexanderbrug
- temporary traffic measures
BUKO - contractorMaurer
Keep following this
Get an email when a new story is published. No account needed.
- ProjectPrins Willem-Alexanderbrug
- SubjectRoad construction
- CompanyBUKO Infrasupport
- CompanyMaurer