Underground risks are rarely visible to the general public, but they can determine whether a project runs smoothly or grinds to a halt. Many infrastructure projects in the Netherlands face setbacks that can also be traced to unexpected ground conditions. On the A2 widening project in Limburg, Boskalis is leaving nothing to chance and, together with Metinco, is pulling out all the stops to map potential underground risks in advance.

A complex part of the A2 project lies near Roosteren. “Here, the motorway runs right alongside the Julianakanaal, which is also higher than the surrounding ground level,” says Marco de Kleine, co-owner of Metinco. “The Geleenbeek flows beneath both the motorway and the canal at this exact location. Over a stretch of just 250 metres, the road, canal, dyke and stream converge. It is a complex knot, where above-ground works are only possible if the ground beneath is fully understood.” For this reason, Boskalis asked Metinco to carry out an advanced geophysical survey on site.

This technique reveals both the layers and objects on the riverbed.

New eco-passage

There are two reasons for studying the ground at this location so ‘meticulously’. “Alongside the existing Geleenbeek crossing, a new culvert is being built to serve as both an eco-passage and an additional outlet for water,” De Kleine continues. “The floods in Valkenburg highlighted the urgent need for robust water drainage in Limburg. During peak flows, streams must be able to discharge water more quickly towards the Maas. At the same time, the A2 and the Julianakanaal form barriers to wildlife. The new corridor must combine both functions.”

Unpredictable ground conditions

Building a culvert beneath a canal that lies higher than ground level and carries ships every day is technically very complex. “The canal cannot simply be closed to traffic for this project, and the stability of the banks must not be put at risk,” De Kleine stresses. “There is also highly variable ground beneath the canal, with gravel deposits that could cause major leaks during construction. Working in gravel can also be technically challenging. Traditional ground investigations, such as boreholes and cone penetration tests, provide point data, which is not always sufficient in an area with complex ground conditions. What lies just a few metres from a borehole or cone penetration test remains uncertain. And that uncertainty is precisely what creates a risk.”

A broadband, low-frequency ground-penetrating radar system reveals objects and subsurface layers in high resolution.

Geophysical techniques

Variations in the ground limit how representative traditional investigation methods, such as boreholes and cone penetration tests, can be when used as the sole source of information. That is why an intensive programme of geophysical techniques was chosen here. “Boskalis deserves credit for that, because in the Netherlands we tend to be rather conservative when it comes to ground investigation,” De Kleine says from experience. “Traditional methods are often the default, but they are far from the only option. On this project, we even used 3D seismic surveying, an approach rarely used in practice in our sector in the Netherlands.”

Detailed picture

Rather than taking measurements only at individual points, Metinco’s broad use of geophysical techniques makes it possible to map volumes. “By measuring the physical properties of the ground, such as electrical conductivity, vibration behaviour and the propagation of radar waves, we generate continuous 2D and even 3D profiles. Hard layers respond to vibrations differently from soft ones; wet or saline ground conducts electricity differently from dry soil. By translating these physical signals into geological interpretations, we build a much more detailed picture of variations in the subsurface,” says Mike van der Werf, co-owner of Metinco.

Set-up for the geoelectrical measurements, which determine the electrical resistivity of the ground.

Iterative process

According to De Kleine, mapping the ground is an iterative process of surveying, modelling, designing and reassessing, with additional boreholes carried out in collaboration with Rijkswaterstaat and Boskalis. Translating geophysical measurements into geotechnical parameters or information is challenging. We often measure physical parameters that differ from those required for the design. Making sure our data provides usable information is one of the biggest challenges. This is only possible through close collaboration between the parties involved. Otherwise, it is as if you are speaking two completely different languages with no interpreter nearby.

This makes it possible to assess different construction scenarios and rule out or identify high-risk options at an early stage.” The result is not absolute certainty. “That is never possible underground, but it does provide a better-informed basis for decision-making. Because safe construction starts with understanding what is happening beneath your feet.”

Have a business enquiry for Boskalis Nederland? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeUnderground construction
  • SubjectRoad construction
  • CompanyBoskalis Nederland
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.